Project Planner: Kraig Tambornini (415) 485-3092
REPORT TO PLANNING COMMISSION for November 15th MEETING
SUBJECT: 397-400 Smith Ranch Road (San Rafael Airport Recreational Facility) –
Review of
Final Environmental Impact Report (FEIR) published for a Zone Change, Master Use
Permit and Environmental and Design Review Permit for proposed recreational
sports
facility project at the San Rafael Airport; APN: 155-230-10,11,12,13,14,15,16);
Planned
Development-Wetland Overlay (PD1764-WO) Zone; Bob Herbst, Applicant; San Rafael
Airport, LLC, Owner; File Number(s): ZC05-01, UP05-08, ED05-15
EXECUTIVE SUMMARY
The City of San Rafael, Community Development Department, Planning Division, has
completed
environmental review for a new recreational facility project proposed on the San
Rafael Airport property,
located off Smith Ranch Road in North San Rafael. The project proposes
construction of an 85,700
square foot multi-use recreational building and outdoor sports fields, with
associated parking, lighting,
fencing and landscaping improvements located on an undeveloped portion of the
airport property. The
property has been developed under the San Rafael Airport Master Plan, approved
in 2001. Planning
applications required for the project include a Zone Change to amend the current
Planned Development
(PD) District to establish recreational uses and development standards, Use
Permit to establish
conditions for facility operations, and Environmental and Design Review Permit
for building and site
improvements. The Commission is responsible for reviewing the Final
Environmental Impact Report
(FEIR) and project zoning entitlements, and providing its recommendation to the
City Council.
The purpose of this hearing is to discuss certification of the project FEIR;
which has been prepared for
the purpose of identifying, evaluating and reducing all potential environmental
impacts of the proposed
development project, and to respond to all comments received during the required
60-day public review
period. The Commission must consider whether to recommend certification of the
FEIR before providing
its recommendation on the Rezoning and related project entitlements. Staff has
prepared a draft
resolution with the findings required to certify the project EIR (Exhibit 2).
Certification of the FEIR does not result in a decision whether to approve or
how to carryout the project. Rather, certification of the
FEIR confirms that the document has been prepared properly in accordance with
the requirements of
CEQA, and that the reviewing agency has considered the information contained in
the document. Review
of the FEIR prior to certification focuses on the response provided to the
comments on the DEIR.
Disagreement over the conclusions of the analysis or the responses to comments
is not a reason to deny
certification of the document.
Prior to approving the project, the Planning Commission must adopt a separate
resolution finding that the
certified FEIR adequately mitigates the projects potentially significant
environmental effects.
A detailed staff report and draft resolutions on the Rezoning, Use Permit and
Environmental and Design Review
Permit entitlements would be presented for the Commission to review and consider
at a separately
noticed public hearing. This would include a draft resolution containing the
CEQA findings of fact and
Mitigation Monitoring and Reporting Program (MMRP) required for approval of the
development project
evaluated by the FEIR. Potential hearing dates for project merits would be
December 13, 2011 and
January 10, 2012.
2 of 28
On May 12, 2009, following a 60-day public review period, the Planning
Commission accepted public
comments on a project Draft EIR (DEIR); in compliance with the requirements of
California
Environmental Quality Act (CEQA). Following the hearing, the Commission directed
staff and the City’s
environmental consultants to prepare responses to the 78 total written comments
received; which
included 6 comments from responsible agencies, 71 comments from non-agencies and
the meeting
minutes containing the oral comments received from public and Commissioners at
the May 12, 2009
hearing. As part of the effort to respond to comments, City staff requested
additional information from the
project geotechnical engineer, John C Hom and Associates, and requested further
analysis and peer
review to be conducted by its environmental consultants.
The further analysis and peer review work included preparation of responses to
comments on biological
resources provided by Monk & Associates, comments on airport hazards by Mead &
Hunt, responses to
comment on air quality impacts associated with aviation activities provided by
Donald Ballantini,
responses to comments on the levee, flooding and sea level rise provided by
Questa Engineering
Corporation, and responses to comments on noise impacts provided by Geir & Geir.
City staff also had a
greenhouse gas assessment prepared for informational purposes, evaluating
regional air quality district
(BAAQMD) thresholds adopted after publication of the DEIR (thus, the new BAAQMD
thresholds do not
apply to this project). The FEIR contains responses to all comments received on
the DEIR, provided in
FEIR Chapter 1. Revisions to the DEIR discussion are provided in FEIR Chapter 2.
An FEIR Appendices
is also provided containing the additional information prepared to augment the
DEIR analysis. The FEIR
represents the conclusive environmental analysis and responses to all comments
made on the DEIR.
Staff and the project environmental consultants will provide a presentation at
the hearing to review the
conclusions of the FEIR and this report. Further responses to any new or
additional comments made on
the FEIR are not required prior to certifying the FEIR.
The FEIR response to comments include 24 Master Responses that address topics
regarding the sites
maximum occupancy calculation, property declaration of restrictions, story pole
placement, headlight
glare, operational impacts on wildlife, revised FEMA flood datum values*, levee
maintenance and
condition, sea level rise and levee breach, water quality, noise, SMART train
operations, growth inducing
effects, greenhouse gasses, and alternative assumptions. As a result of
preparing the responses to
comments, revisions have been made to the DEIR to clarify some of the discussion
found in Chapter 13
Transportation and Traffic, Chapter 14 Cumulative Impacts, Chapter 15 Climate
Change and Chapter 16
Alternatives. In addition, mitigation measures for Biological Resource,
Hydrology and Water Quality and
Noise impacts have been revised (FEIR Chapter 2, revised Table 2-1). These
revisions to the DEIR
discussion and mitigation measures clarify, augment or expand discussion
contained in the DEIR. Minor
revisions to the project site plan have also been identified and would be
required for project approval.
The project would not result in any significant unavoidable impacts, and
revisions made as a result of
preparing responses to the DEIR have not resulted in any additional impacts,
required new or
substantially different mitigation measures, or triggered recirculation of the
document.
RECOMMENDATION
It is recommended that the Planning Commission take the following actions on the
Recreational Facility
Project, amending the current San Rafael Airport Master Plan:
1. Recommend to the City Council Certification of the FEIR for the San Rafael
Airport Recreational
Facility Project by adopting the attached Resolution (Exhibit 2).
* The change from the 1929 NGVD to more recent NAVD results in a +2.67 increase
in the datum value but this
does not reflect change in site hydrology. In this report, staff has continued
to use the old 1929 NGVD datum value
for reference, in order to avoid confusion from switching between NGVD and NAVD
datum values.
3 of 28
2. Direct staff to schedule the project for Planning Commission review and
recommendation on the
project merits (i.e., PD Rezoning, Use Permit and Environmental and Design
Review Permit
zoning entitlement requests).
As mentioned previously, the Commission must recommend certification of the FEIR
before it can
consider the project zoning entitlements. If certification is not recommended,
the project could only
proceed without further environmental review by filing of an appeal to the City
Council.
PROPERTY FACTS
Address/Location: 397-400 Smith Ranch Road Parcel Number(s): 155-230-10 thru -16
Property Size: 16.6-acres of 119.5-acre site Neighborhood: Smith Ranch
Site Characteristics
General Plan Designation Zoning Designation Existing Land-Use
Project Site: Airport/Recreation PD1764-WO & W Airport & Assoc. Use
North: P/OS, Cons, Low Den Res P/OS McInnis Park
South: P/OS, Cons, Low Den Res Unincorporated Santa Venetia Residen
East: P/OS, Cons, Low Den Res Unincorporated Santa Venetia & Bay
West: Medium Density Residential PD1626-WO&PD1399 Contempo Marin &
Captains Cove Resid
Site Description/Setting:
The airport property consists of a single, 119.52-acre parcel (Parcel B on
Parcel Map 70 Civic Center
North) which was recorded in December 1983. The project area comprises a
16.6-acre portion of the
airport site, located between the existing runway and Gallinas Creek, east of
the existing airport hangars.
This area is currently undeveloped, annually disked and mowed grasslands and
improved only with a
man-made drainage ditch and row of eucalyptus trees. The property is a
relatively level site consisting of
formerly submerged tidelands situated at approximately 0-3 feet elevation above
mean sea level, and
bordered by the North and South Forks of Gallinas Creek. The site is protected
by a perimeter levee
system extending approximately 12,000 linear feet and connecting with the
Contempo Marin levee
system, which as a whole, provides flood protection to the area. The levees
around the site are
established at 9-feet above mean sea level, and built circa 1940 as agricultural
levees to reclaim tidally
influenced lands for agricultural use. Prior to this time, agricultural use was
initiated circa 1915 with
purported fill placed near the existing airport operations (aka, Smith Ranch).
Delineated wetlands (under jurisdiction of US Army Corps of Engineers) are
located between the
proposed recreational facility site (project area) and the levee along the North
Fork of Gallinas Creek.
Drainage from the eastern portion of the site and project area is collected and
transported through
existing man-made drainage swales that run parallel along the north side of the
proposed building and
the airport runway. The ditches carry runoff to an existing pump-house near the
northeastern corner of
the airport site, where it is pumped into the creek. The pump-house is located
on state lands, which are
managed by Marin County. Access to the site is provided from Smith Ranch Road
across a private
roadway and bridge. The bridge and the road access are off-site, crossing a
private easement within the
Captains Cove development (formerly Smith Ranch subdivision lands) and public
lands (North Fork of
Gallinas Creek).
The existing airport facility primarily operates for small private aircraft
flights and hangars for aircraft
based at the site, located in the westerly portion of the property. This area
includes hangars for 100-
based aircraft, an aviation service use, airport administrative offices, two
residential units, and 12 non
4 of 28
avation uses. There are 14-acres of undeveloped land south of the runway within
the City jurisdiction.
Another undeveloped 45-acre (+/-) portion of airport property lies within County
jurisdiction
(unincorporated). This area primarily consists of undeveloped flat lands,
portions of the levee along the
South Fork of Gallinas Creek, and extending under the South Fork of Gallinas
Creek waterway. The
majority of the airport property (including all existing airport improvements
and the proposed project site
area) are within the City of San Rafael jurisdiction. The developed and
undeveloped land areas on the
airport property are further identified as follows:
o San Rafael Airport hangars, structures and runway are located on area
identified as APN 155-230-
11; (+/-) 38-acres
o Proposed recreational facility, wetlands and creek setback buffer, access road
extension and related
improvements are located on the area identified as APN 155-230-12; (+/-)
16.6-acres
o Vacant undeveloped lands located south of the runway and within the City of
San Rafael corporate
boundary are identified as APN 155-230-13; (+/-) 14-acres
o Vacant undeveloped lands located south of the runway and outside City of San
Rafael corporate
boundary (within County of Marin jurisdiction), that contain southerly portions
of the levee and
extending under the South Fork of Gallinas Creek are identified as APN’s
155-230-14 and 15; (+/-)
45-acres
The 441-acre McInnis Regional Park and golf course, and a public walking path
are located just
north/northeast of the site (across Gallinas Creek). Sonoma-Marin rail
right-of-way runs along the
southwest to northwest boundary and separates the site from the Contempo Marin
and Captains Cove
residential neighborhood areas, and two additional residential units located
along the existing access
road. The unincorporated Santa Venetia residential neighborhood is located to
the south/southeast
(across the South Fork of Gallinas Creek). US Highway 101 is located
approximately 1-mile to the west.
Other prominent visual features in the area include Marin County Civic Center,
which is 1-mile to the
southwest, the nearby San Pedro Ridge to the south, Mount Tamalpais to the west
and San Pablo Bay
located to the east. A detailed description of the setting is also contained in
the DEIR, Chapter 3, pages
3-1 thru 3-4.
BACKGROUND
The subject applications for the recreational facility were filed in March 2005.
Following the publication
and hearing on a draft Initial Study and Negative Declaration that was prepared
for the project in 2006,
the City concluded that it must prepare an Environmental Impact Report (EIR) for
the project, and
required California Clapper Rail protocol surveys to be conducted in 2007. On
May 12, 2009, following
completion of the project Draft Environmental Impact Report (DEIR) in March
2009, the Planning
Commission conducted a public hearing and accepted comments on the DEIR and
directed staff to
prepare responses to all comments received in compliance with CEQA. The Final
EIR (FEIR) was
completed and published in August 2011 and distributed in September 2011,
following detailed review of
all comments and the responses prepared by the City’s environmental consultants
and CEQA attorney.
Certification of the FEIR is the first step in determining whether the project
is ready for review of its
zoning entitlements. A certified EIR is required for the project before the City
can decide whether it would
approve the project in its current or modified fashion.
PROJECT DESCRIPTION
The project proposes construction of a new, multi-purpose private recreational
facility that would develop
approximately 9.1-acres of vacant land on the San Rafael Airport site (with new
hardscape, roadway and
parking paving, structures and landscape improvements associated with the
facility). The project site is
located between the existing airport runway and North Fork of Gallinas Creek,
east of the existing airport
5 of 28
hangars and site access road. An additional approximately 4-acres of project
site area would be
maintained as a wetland and creek buffer area; located between the proposed
recreational facility
improvements and the creek bank. The recreational facility development would be
in addition to the
existing approved and built airport facility uses. The proposed recreational
facility development consists
of the following uses and components:
Recreational Uses:
• An 85,700-square-foot multi-purpose recreational building, 39-foot-6-inch tall
(overall height), with the
following use areas:
o Multi-purpose gymnasium area for recreational uses. The project plans propose
to improve
the building with two indoor soccer sports fields
and two multi-purpose gymnasium sport
courts, common locker and restroom areas on the 71,300-square-foot ground floor
level, and
o A 14,400-square-foot mezzanine level. This level would include an ancillary
viewing area,
approximately 4,092 square foot café area with dedicated countertop seating for
20 people,
restrooms, sports shop, administrative offices and meeting room uses. The
meeting room
would be available for private ancillary recreational activities such as
birthday parties and
similar group events or meetings, and would be offered as complimentary use of
local seniors
for activities and for neighborhood groups who need meeting space.
• Lighted all-weather outdoor sports field and an unlighted outdoor grass
warm-up field. The project
proposes to develop the lighted outdoor field as a
200-foot by 300-foot sized soccer field with all
weather field turf, to allow year round use.
Facility Use and Hours of Operation:
The use proposes to operate 7 days per week. The applicant anticipates up to 700
daily users within the
indoor facilities and 300 daily users for the outdoor field, plus up to 12
equivalent full-time employees.
The project would not be open during the weekday AM traffic peak hour. The
proposed hours of
operation are as follows:
Indoor Facility: 9AM to 11PM Sunday through Thursday (weekdays)
9AM to 12AM Friday and Saturday (weekends)
Outdoor Facility: 9AM to 11PM* Sunday through Thursday (weekdays)
9AM to 12AM* Friday and Saturday (weekends)
*As a result of the mitigation measures contained in the FEIR, to address light
and noise impacts on
wildlife and nearby residents, an outdoor event curfew would limit field usage
to no later than 10PM, and
with a potential for earlier curfew of 9PM on weekdays.
Site Design and Access:
The project proposes to develop the site in compliance with standards
established by the US Green
Building Council, with a two-year construction timeframe. Features proposed to
be incorporated into the
project design include solar roof panels and energy efficient field lighting.
Site improvements include
exterior lighting, landscaping and drainage. The building finished pad elevation
would be raised with fill
soils to achieve +1.0 NGVD and the building would be dry flood-proofed
(impermeable to penetration by
floodwaters) to +7.0 NGVD in compliance with FEMA standards.
6 of 28
Project improvements include extension of a new 30-foot wide paved private
roadway including a 5-foot
pedestrian walkway access extending from the end of the existing access road.
The new roadway
elevation would be raised to meet the parking lot elevation of approximately 2.0
feet NGVD. All
development has been designed to avoid conflict with an aircraft transition
safety zone (i.e., 7:1
‘ascending clear zone’). This zone extends at an incline angle from the edge of
the 125-foot airport
‘aviation clear zone’ setback to the sky (see Plan Sheet A-5). There would be
184 paved parking spaces,
a turnaround drop off area, and 86 unpaved parking spaces provided. This parking
exceeds the 222
space parking demand calculated for the proposed facility (see DEIR Appendix K,
Fehr & Peers traffic
report, page 19). In addition, the existing bridge crossing over the North Fork
of Gallinas Creek would be
replaced with a new two-lane, 25-foot wide steel truss bridge deck.
Note: During preparation of the FEIR, staff required site plan revisions that
are deemed to be minor in
order to confirm the following items could be addressed:
o The existing eucalyptus trees along the north side of the building were
indicated on project plans but
were not surveyed. It has been established that the building location extends
into the trees along the
north building wall. The FEIR requires that all exterior site work must occur
outside of raptor nesting
periods. Further, replacement of landscape screening is required along the north
side of the building,
to help screen the building. The revision to the site plan is intended to
clearly establish the need for
tree removal and replacement in this area, which is within the scope of the
impacts evaluated for the
project.
o The Fire Department requires a new fire access along the west side of the
building along with a 5-
foot pathway behind the building, to address current fire requirements. The
building is setback 55-
feet from the wetland. Thus, installing a 5-foot path behind the building would
maintain compliance
with the minimum required 50-foot wetland setback.
o Three roll-up doors shown on the north side of the building would likely need
to be eliminated. Thus,
all deliveries of large equipment and supplies for the building would occur at
the east, west and south
building sides.
Exterior Lighting:
The project would utilize four types of lights, as follows (see Plan Sheets A-1
and A-7 for locations):
• Building Entry: Eight (8) 42-watt compact fluorescent under-canopy lights 20
feet on-center at the
three building entryways.
• Main Building Walls: Twenty-three (23) 150-watt metal halide wall-mounted
lamps at 50 feet oncenter,
14-feet above finished floor.
• Access Road/Parking Lot Perimeter: Thirty-one (31) 42” high 70-watt round
bollards at 40 feet oncenter
along the access road and parking lot perimeter.
• Parking Lots: Nineteen (19) 14-foot tall poles with 150-watt metal halide
lamps on two-way side pole
mounted fixtures at 40-feet on-center.
• Field Lights: Four (4) 40-foot high poles on the north side of the field with
energy efficient “MUSCO
Green Generation” or equivalent 1500 watt metal halide lamps, 3 luminaries per
pole, at 30 feet oncenter
and four (4) 23-foot high poles with 2 luminaries per pole on the south side of
the field.
Zoning Entitlements:
The project includes requests for the following required zoning entitlements:
7 of 28
?? Zone Change: ZC05-01 to amend the Planned Development Ordinance
(PD-1764)–Wetland Overlay
(WO) district to include development standards for the proposed recreational
facility use.
?? Use Permit: UP05-08 (amendment to Master Use Permit UP99-9) to establish
conditions under which
the proposed recreation use should be allowed to operate.
?? Environmental and Design Review Permit: ED05-15 to approve the design of the
recreation building
and site improvements.
ENVIRONMENTAL REVIEW ANALYSIS
Environmental Review Process to Date
The following discussion addresses the California Environmental Quality Act (CEQA)
environmental
review process followed for the project, summarizes the conclusions for each of
the environmental topic
area discussed in the DEIR, and identifies the revisions to discussion and
mitigation measures that have
been made in response to comments on the DEIR. The DEIR and FEIR response to
comments
documents comprise the entire project FEIR. The project FEIR CEQA document must
be certified as
having appropriately analyzed the potential physical effects of the project on
the environment. This
analysis must be completed before the City can take action to approve the
development project. The
noticing that has been provided for the DEIR/FEIR, as required by CEQA, is
summarized as follows:
Notice of Preparation (NOP): Consistent with the California Environmental
Quality Act (CEQA)
Guidelines, on October 10, 2007 the City prepared and published a Notice of
Preparation (NOP) of an
Environmental Impact Report for the San Rafael Airport Recreational Facility, to
obtain updated
comments from responsible and trustee agencies and interested parties. Following
the required 30-day
public review period, comments received were forwarded to the EIR consultant. As
noted above, the
decision to prepare an EIR was previously made following hearings on the project
by the Planning
Commission. A formal scoping meeting was not required, nor conducted, given the
amount of public
input provided at the previous public hearings on the project and published
draft Initial Study/Mitigated
Negative Declaration. As a result of the public hearings and public input, it
was determined that the EIR
would focus on the following topic areas:
• Land Use and Planning
• Aesthetics
• Air Quality
• Biological Resources
• Cultural and Historic Resources
• Geology and Soils
• Hazards
• Hydrology and Water Quality
• Noise
• Transportation and Traffic
• Other Environmental Effects
• Alternatives
Additionally, the scope of work was expanded in response to recently enacted
environmental legislation
to address the following:
• Climate Change
8 of 28
The scope included detailed review of biological habitat issues, specifically to
assess potential California
Clapper rail impacts; aeronautical safety hazard study; peer review of noise
analysis; traffic analysis of
operations during the 4PM to 6PM evening peak hour; visual impact analysis; and
light and glare impacts
from the proposed outdoor field lights. The environmental topic areas addressed
in the DEIR are
summarized on DEIR Chapter 3 pages 3-51 thru 3-53 (Project Description).
Notice of Completion and Publication of DEIR: The DEIR was completed and
distributed along with a
Notice of Completion (NOC) on March 11, 2009 pursuant to Section 15372 of the
California
Environmental Quality Act (CEQA) Guidelines. A Notice of Availability and Public
Hearing was also
mailed to all interested and affected parties, including property owners within
1,000 feet of the subject
property. In addition, the NOC was published in the Marin IJ, posted on the
property and at the nearby
McInnis Park, and copies of the NOC and DEIR were made available online and
distributed to several
public locations. Publication and mailing of the notices and distribution of the
DEIR initiated a 60-day
public review period, during which time all interested parties, persons and
agencies were encouraged to
submit comments on the adequacy of the DEIR. Staff also held an informational
meeting on March 25th
to inform representatives of neighborhood and interested groups about the DEIR
review process and
conclusions. On April 23, 2009, a supplemental notice was distributed to all
parties, and the State
Clearinghouse, reporting that the review and comment period was extended to May
12, 2009 (61 days).
At the DEIR hearing the Commissioners identified concerns with "piece-meal"
development of the site,
adequacy of the noise analysis and Clapper rail study, geologic investigation of
the site and levee, levee
stability and maintenance, impacts of SMART train operations, need for
clarification regarding airport
hazards and mitigation, impacts at unsignalized intersections and peak traffic
impacts, and the adequacy
and enforcement of conservation area protections. The minutes of the hearing can
be found on FEIR
page C&R-824 through C&R-833. Responses to the Commissioners comments begin on
FEIR page
C&R-851. Following the hearing, staff directed its environmental consultants to
prepare a FEIR
responding to all of the comments and data that had been received during the
public comment period. In
providing responses to all the comments, the City’s environmental consultants
were directed to prepare
additional and expanded analysis of several topic areas, including:
• Climate change impacts regarding sea level rise and greenhouse gas emissions;
• Geology and Hydrology impacts relate to levee construction; and
• Project alternatives
Additionally, information and analysis methods for evaluating potential global
warming effects continued
to evolve during preparation of the environmental document. The DEIR analysis
has been prepared
using the qualitative threshold to determine whether the project would conflict
with any of the programs
encouraged under AB32 (Global Warming Solutions Act). This is the appropriate
threshold applicable at
the time of preparation and publication of the DEIR. However, in order to
fulfill the role of CEQA as an
informational document, staff directed the City’s environmental consultants to
prepare a quantitative
greenhouse gas analysis using more recent BAAQMD thresholds adopted in June
2010; after publication
and release of the DEIR. Although this analysis is not required since the law
was adopted after the
preparation of the DEIR, staff found that including the greenhouse gas emissions
would be valuable
information to have and help fulfill the primary goal of CEQA, to present an
informational document.
Finally, a detailed legal review of the revisions made to the DEIR was conducted
by City CEQA counsel,
to confirm that the document changes would not trigger re-circulation pursuant
to CEQA Guidelines
section 15088.5.
Notice of Availability of FEIR: On September 8, 2011 copies of FEIR were
delivered to the Planning
Commission, City Council and 6 public agencies that commented on the project,
with electronic (CD)
copies delivered to the 71 non-agency commenter’s. Mailed copies of the notice
of completion of the
9 of 28
FEIR were sent to surrounding residents and property owners and interested
parties and groups
requesting notification on the project. Staff has also emailed notification of
the FEIR completion to
individuals and groups that have provided email addresses.
Summary of Final EIR / Response to Comments
The published FEIR contains Chapter 1: Response to Comments, Chapter 2:
Revisions of the DEIR, and
the FEIR appendices, and incorporates the previously published DEIR and DEIR
Volume II: Technical
Appendices. FEIR Chapter 1 responds to all comments made on the DEIR and
includes 24 Master
Responses that address multiple comments received on similar topic areas (FEIR
pages C&R-8 through
C&R-53). FEIR Chapter 2 includes revisions, corrections and modifications made
to the discussion in the
DEIR. All potential impacts and proposed mitigation measures are summarized in
the FEIR revised Table
2-1 (commencing on FEIR page R-52).
As noted in the Executive Summary above, the FEIR includes revisions to
discussion in Chapter 13
Transportation and Traffic, Chapter 14 Cumulative Impacts, Chapter 15 Climate
Change and Chapter 16
Alternatives. In addition, mitigation measures for Biological Resource,
Hydrology and Water Quality and
Noise impacts have been modified in FEIR Chapter 2, revised Table 2-1. Detailed
discussion of revisions
made in response to comments on the DEIR has been provided below in the
appropriate sections of this
report. The project FEIR has concluded that all of the potential impacts
associated with the project can
be mitigated to a less-than-significant level. The project has not resulted in
any potentially significant
unavoidable impacts (significant environmental impacts for which there is no
mitigation or that cannot be
mitigated to less-than-significant levels). The potential environmental effects
that would result in lessthan-
significant effects with implementation of mitigation measures have been
identified in the following
environmental impact categories:
• Aesthetics
• Air Quality
• Biological Resources
• Cultural Resources
• Geology and Soils
• Hazards
• Hydrology and Water Quality
• Noise
Mitigation measures required for the potentially significant impacts identified
in these categories primarily
establish controls on facility construction and design, which are intended to
protect wildlife and minimize
construction noise and dust. Several design-related mitigation measures have
been identified to address
the building height, construction and facility occupancy limits that would
mitigate potential safety conflicts
between the use and aircraft in flight. Operational measures that have been
identified include the
implementation of a 10PM outdoor event curfew, which would mitigate noise and
light impacts on wildlife
and nearby residential areas. There were no potential impacts identified that
would require mitigation in
the areas of Land Use and Planning, Traffic, Climate Change, or Other
Environmental Effects.
Additionally, no potentially significant unavoidable impacts have been
identified as a result of the
additional review conducted during preparation of the FEIR/Response to Comments.
A detailed
discussion of the FEIR analysis and changes made in response to comments is
provided for each
environmental topic area, as follows:
10 of 28
Land Use and Planning (Chapter 4, DEIR pages 4-1 thru 4-20)
The Land Use and Planning section provides an overview of the site location,
existing and surrounding
uses, history, current entitlements, and land use restrictions. The current
entitlements permit a private,
state-regulated airport with 100 hangars and 12 non-aviation light industrial
businesses. A project would
result in a significant land use impact if it: a) physically divides or disrupts
a community, or b) is in conflict
with the General Plan, any other planning program or conservation plan.
The San Rafael General Plan 2020 contains goals and policies applicable to the
site and the
environmental characteristics found on the site. The PD zoning district is used
to implement the General
Plan Airport/Recreation land use designation. The General Plan and –WO zoning
regulations also
specify development setbacks from wetlands and creeks. The proposed project has
been evaluated for
consistency with the San Rafael General Plan 2020 (DEIR Appendix C). The project
impacts were
identified as less-than-significant based upon: a) recreational uses may be
conditionally permitted; and b)
the project provides the minimum required 50-foot setbacks from designated
wetlands north of the
building and 100-foot setbacks from the top of bank of Gallinas Creek (see DEIR
Figure 3-3, Site Plan).
The project would not result in any potentially significant land use impacts.
Therefore, no mitigation
measures have been recommended or required.
The comments provided on the Land Use and Planning section have not resulted in
any changes to the
DEIR discussion. The FEIR Master Response 2 (PD-2) has been provided to further
discuss and confirm
the conclusions of the DEIR analysis; primarily that the private and public
recreational uses category
allowed under the property Declaration of Restrictions is broad enough to
include structures.
Land Use Covenant
The “public and private recreational uses” term used in the covenant is
unqualified; other than stating
that the use may be for public or private recreational uses. This restriction
was recorded on the property
in 1983 as a condition of parcel map 21 PM 70, which created two lots (Parcel A
and Parcel B). This is a
three-party agreement between the City, County of Marin and property owner. The
agreement is in favor
of the City and County by establishing a restriction on future land uses for the
airport parcel (Parcel B);
which is partially within County jurisdiction. The airport property Parcel B was
not a part of the adjacent
Civic Center North Master Plan, which included Parcel A. The idea for the
covenant was first raised at
the City Council meetings on the parcel map conducted February 22 and March 21,
1983, after the
Planning Commission hearings on the project. This idea was introduced by a Marin
County supervisor.
The property owner agreed to accept a limit on future land uses on the airport
as a condition of the parcel
map. The subsequent purchaser of the property challenged the validity of the
restriction, and the
covenant was upheld. The covenant was not required to transfer any development
rights to adjacent
lands. The City had a formal process for this to occur at the time, and this
process was not applied to this
case.
While it is clear the covenant intended to restrict future land uses on the
site, and the site has been
maintained with limited development intensity, the terms of the covenant do not
provide any specific
limits on development intensity. Further, it is worth noting that the General
Plan 2000 had a land use
policy that would have allowed more intense residential development of the site,
in the event that the
land use restriction were lifted. Staff has reviewed the project files related
to the covenant, and cannot
establish specific limits on intensity of the permitted land uses. In fact, a
review of the City Zoning
Ordinance in effect in 1983 (at the time the covenant was executed) reveals that
the “Recreational Uses”
zoning classification included a broad range of recreational activities, such as
parks, gymnasiums, public
pools, play or game courts including tennis and handBAll, skating rinks without
fixed seats, marinas, golf
course and driving range, pool or billiard halls and bowling alleys. Thus, a
recreational land use category
11 of 28
was established in 1983 that included a variety of recreational activities that
included uses in buildings;
which is similar to the current zoning classification. It stands to reason that
if the intent of the covenant
was to further limit the intensity of recreational use, the covenant would have
specified further limitations.
Opinions that the restriction intended to preclude the development intensity
proposed by the project are
unsupported by evidence in the City zoning record, and neither the City nor the
County could reject filing
of the project applications based on the terms of the covenant. However, this
does not limit the City’s
review authority over the proposed development project.
The City Attorney and Marin County Counsel have both reviewed the declaration
and confirmed that the
covenant is, as stated, a restriction on future land uses of the property; which
does not preclude the level
of development proposed, including construction of a recreational facility with
structures. Further, the City
General Plan 2020 Airport/Recreation land use designation does not restrict the
type of private or public
recreational uses that could be proposed and considered by the City for this
site. Questions and
concerns regarding the City’s review and enforcement of the covenant restriction
on the potential land
uses for the property have been resolved from a legal and land use standpoint,
and the FEIR
appropriately evaluates the potential environmental impacts of the level of
development proposed
consistent with this determination. Any remaining disagreement over the intent
of the 1983 covenant is
not an environmental issue. Rather, this may be a topic for further discussion
on the merits of the project,
i.e., the decision on whether or how to implement the project.
Aesthetics (Chapter 5, DEIR pages 5-1 thru 5-36)
The Aesthetics section describes the flat land characteristics of the property,
and its relationship to the
nearby McInnis Park regional park, and surrounding hillsides and ridgelines. The
project site currently
maintains substantially unobstructed public views from McInnis Park and pathways
along Gallinas Creek
toward the historically significant Marin County Civic Center building, the
nearby San Pedro Ridge and
more distant Mount Tamalpais. The public views and potential lighting impacts
are subject to review for
conformance with General Plan 2020 Policies CD-5 (Views) and CD-19 (Lighting),
Zoning Code Section
14.25.050.F.4 (Exterior Lighting), and the San Rafael Design Guidelines lighting
criteria. Project impacts
would be significant if the project would:
a) have a substantial adverse affect on a scenic vista;
b) damage scenic resources;
c) substantially degrade the existing visual character or quality of the site
and its surroundings; or
d) create a new source of substantial light or glare, which would adversely
affect day or nighttime views in the area.
The threshold for a significant impact on public views was identified as the
loss of one-half the view of
the resource (e.g., project impairing one-half of the view). The City does not
have a specific maximum
nighttime lighting threshold. The Police Department recommends minimum levels
for security, including
recommended 1-footcandle intensity at ground level overlap in parking areas,
walkways and building
entrances. The Zoning Ordinance Chapter 25 Design Criteria states that lighting
should provide safety
for building occupants but not create glare or hazard on adjoining streets or be
annoying to adjacent
properties or residential areas. The City has an informal policy to maintain low
lighting levels, and require
shielding of light sources to avoid spillover off-site. Given the site location
at the edge of urban
development, the projects lighting impacts were considered potentially
significant if average intensity
exceeds 1.0-foot-candle or results in significant spillover into adjacent areas.
Four prominent public views were identified and photo-simulations were prepared
to evaluate the
project’s potential aesthetic effects (DEIR Figures 5-2, 5-3, 5-4 and 5-5).
These views and photosimulations
were presented and accepted as appropriate at noticed public hearings held prior
to the
preparation of the DEIR. These views include two vantage points looking south
across the site from
McInnis Park and two views looking west across the site from the creek and path.
Photometric studies
12 of 28
were also prepared to evaluate light and glare (DEIR, Figures 5-6 and 5-7). As a
result of this analysis,
the following potentially significant impacts were identified:
View Impacts
The analysis has concluded that the new building and improvements would
potentially affect public views
of the Civic Center from certain portions of the trail along the north shore of
Gallinas Creek and
waterway, and would partially block a portion of the public views of surrounding
hillsides and Mount
Tamalpais, as viewed from the regional park, creek and trails. The amount of
public view blockage is
considered to be less-than-significant because the development would only block
less than 1/3rd of the
bottom view of hills from public places, would not significantly block public
views of the Civic Center from
public places, and would not silhouette above a scenic vista or ridgeline.
Lighting Impacts
The lighting levels in the building and parking lot area (12.2 foot-candle max.
intensity; with 1.84 average
foot-candles), are considered relatively low level as compared to urban
development within the City. The
project’s average intensity would be 2 foot-candles, including lighting of the
soccer field which ranges
from 14 to 71-footcandles on the field area. A 1 foot-candle threshold has been
established for purposes
of analyses in this environmental impact report, due to the location of the site
at the edge of the urban
development and in an undeveloped area in proximity to public lands. This would
establish minimum
level of lighting for safety and security of occupants at this location. As a
result of this threshold, the
average lighting levels generated as a result of the project have been
considered potentially significant.
Two mitigation measures have been required to mitigate the potential impact from
addition of nighttime
lighting in the area to less-than-significant levels.
MM Aesth-1a requires Design Review Board approval of the lighting plan and
establishes
performance measures including a 90-day review of lighting following
installation, that field lighting is
turned off at 10PM, and site lighting be turned off by 12:30AM. Staff notes that
this mitigation requires
that outdoor field use end earlier, at 10PM, whereas the project proposes to
operate outdoor fields
until 11PM on weekdays and 12AM on the weekend. (DEIR page 5-35)
MM Aesth-1b requires Design Review Board approval of final colors and
landscaping details to
ensure potential daytime glare impacts are minimized and that the gaps in the
tree row along the
north side of the building are filled-in, as proposed. (DEIR page 5-35)
The public comments on aesthetic impacts analyzed in the DEIR have not required
changes to the DEIR
discussion. Master Responses 3 and 4 (AES-1 & AES-2) have been provided to
further discuss and
confirm the DEIR conclusions that the project adequately analyzed the visual
impacts of the project. This
analysis concludes that the project would not have a significant visual effect
on scenic views or vistas as
a result of construction of a new building on site, nor result in a significant
effect as a result of the new
lighting or from vehicle headlight glare on the nearby residences. The project
mitigation measures (which
require DRB review of the final lighting details to assure 1 foot-candle
intensity is achieved at the edge of
the conservation area and project boundary) is a typical City-wide standard for
projects, and can be
readily implemented and accomplished within the parameters of the lighting and
photometric plan
presented for this project.
Concerning glare impacts from vehicle headlights, the discussion on FEIR page
C&R-19 concludes that
a condition of approval that has been previously offered by the applicant to
construct a wall or hedge
along the access road would sufficiently address concerns with headlight glare;
which is not identified as
a visually significant environmental impact. FEIR figures 1 and 2, page C&R-17
through C&R-19, show
13 of 28
the relationship between the nearest residences and the access road and bridge.
Vehicle headlights
would not appear to directly shine into the nearest units, and would be
substantially reduced through
installation of a screen wall or hedge on-site or along the access roadway.
Adjustments that are required to address updated fire access requirements,
relocation of rollup doors
and removal of trees would minimally impact the project, and are within the
scope of the project
description. Although CEQA permits and encourages project revision made to
reduce environmental
impacts, the revisions that have been identified as required are considered to
be related to project merits.
Removal of trees must be reviewed against the discussion in DEIR Chapter 5. On
DEIR page 5-24, it
states that the trees serve to reduce the visual impact and mass of the
structure. Change in visual
impacts must be compatible with the analysis of this Chapter.
The significance thresholds for measuring Aesthetic impacts are as follows:
• Would the project have a substantial adverse effect on a scenic vista
• Would the project substantially damage scenic resources, including, but not
limited to, trees, rock
outcroppings, and historic buildings within a state scenic highway
• Would the project substantially degrade the existing visual character or
quality of the site and its surroundings
• Would the project create a new source of substantial light or glare, which
would adversely affect day
or nighttime views in the area
The only potentially applicable criteria is identified in the third bullet
point. Review of the analysis on
DEIR page 5-24 includes an analysis of the building in context with the entire
area. The trees help
integrate the building by screening. However, as noted above, new landscape
screening is also similarly
required to achieve this result. Therefore, removal and replacement of trees
along this edge of the
building would not conflict with the analysis and impact conclusions contained
in the DEIR Chapter 5.
Air Quality (Chapter 6, DEIR pages 6-1 through 6-22)
Air Quality is regulated by the regional Bay Area Air Quality Management
District (BAAQMD). The
standards for the region are set by the state California Air Resources Board, a
department of the
CalEPA. The Federal Clean Air Act is the principal regulatory mechanism. The
BAAQMD adopted the
Clean Air Plan 2000 for the region. Assessment of Air Quality is based on the
1999 BAAQMD CEQA
Guidelines. The DEIR evaluates both short-term construction and long-term
operational air quality
impacts.
The primary sources of contamination would result from project related vehicle
traffic, construction
vehicles and grading activities, and building fuel consumption for heating and
cooling systems. Impacts
would be potentially significant if they would: a) conflict with the BAAQMD Air
Quality Plan; b) violate an
air quality standard; c) increase a criteria pollutant for a non-attainment
area; d) expose sensitive
receptors to pollutants; or e) create objectionable odors affecting substantial
numbers of people. A
project that would include a general plan amendment for more intense development
of a site, or
development that generates more than 2,000 daily vehicle trips (ADT) could be
considered significant.
The General Plan includes policies AW-2 (Land Use Compatibility), AW-3 (Air
Quality and Other
Processes) and AW-4 (Particulate Matter Pollution Reduction) to ensure excellent
air quality is achieved
by promoting compatible land uses, buffers and setbacks, particulate matter
controls, and design that will
encourage alternate modes of transportation. Generally, a use that is consistent
with the City General
Plan may be concluded to be consistent with the BAAQMD air quality plan.
Although the project would
remain consistent with the General Plan and would not exceed 2,000 ADT, air
quality modeling was still
conducted for the project using the URBEMIS 2007 modeling program. URBEMIS is a
modeling software
14 of 28
tool that is used to measure such impacts for compliance with air district
rules. This modeling was
completed as a conservative measure to confirm that the proposed new development
would remain in
compliance with the BAAQMD Air Quality Plan, given that the General Plan 2020
EIR land use analysis
did not specifically assess the proposed recreational land use. The following
project air quality impacts
were identified:
Operational Impacts
Based on the results of the URBEMIS modeling and number of anticipated 1,701
daily trips (ADT), long
term project operations would not exceed the BAAQMD established daily threshold
of 2,000 ADT. The
FEIR further discusses potential air quality impacts associated with aviation,
on FEIR pages C&R-533
through C&R-535, response 45-42. The response notes that the small airplanes at
the site primarily use
aviation gasoline, and that “the level or density of criteria pollutant emission
along the runway is far less
than along a lightly-traveled rural two-lane road, and would pose no hazard to
persons using the
proposed recreational facility.” Aviation gasoline does contain lead. However,
the strength of the
emission associated with the airport is identified as quite small, and aviation
gas contains a fraction of
lead that was used in automobile gasoline before its use was phased out. The
airport averages only 20
landing/takeoffs per day. Emissions taking place near the ground that would
potentially affect
neighboring properties are considered to be negligible.
Construction Impacts
Short-term construction impacts are assumed for most large sized development
projects (e.g., projects
that would not be exempt from CEQA) involving new construction and grading.
Standard mitigation
measures are employed to ensure construction impacts (e.g., vehicle fumes and
dust) would be
mitigated to a less-than-significant level.
The following mitigation measures were identified to address potentially
significant construction related impacts.
MM AQ-1a through MM AQ-1c (Construction Impact) establish vehicle emission and
dust control
measures required during grading and construction activities (DEIR page 6-19).
There were no substantial comments made on the DEIR that required further
discussion or revision in
this section of the FEIR. Thus, there have been no modifications proposed to the
DEIR discussion or
DEIR mitigation measures.
Biological Resources (Chapter 7, DEIR pages 7-1 through 7-82)
The airport property contains ruderal grasslands north of the airport runway,
which are within the project
site area. Additionally, six jurisdictional wetland areas have been delineated
on the north side of the
proposed development (see DEIR page 7-27, Figure 7-1). The grasslands, including
the area containing
the nearby delineated wetlands, are disked and mowed regularly to prevent
potential wildlife and aircraft
collisions. This practice is in keeping with FAA recommended practices, and may
continue. The US
Army Corps of Engineers established a jurisdictional delineation of the wetlands
(to the north of the
building), and a Streambed Alteration Permit has been issued by the Department
of Fish and Game for
the proposed bridge deck replacement. The North Fork of Gallinas Creek contains
habitat for fish and
wildlife. The Federal and State Endangered Species Acts protect threatened or
endangered species and
their habitats. Project impacts would be potentially significant if they would
have a substantial adverse
effect on or result in loss or harm to a protected species or habitat.
Initial biological studies were prepared by WRA, biological consultants and
submitted with the planning
applications. Monk and Associates (M&A) biological consultants were hired to
re-evaluate potential
15 of 28
impacts on special status plant and animal species (DEIR Appendix E); initially
evaluated by WRA and
peer reviewed by Zander and Associates. Protocol surveys were conducted by M&A
from February
through July 2007, and two pairs of California Clapper rails were observed or
heard on the north side of
Gallinas Creek. Threatened steelhead trout species also have been identified as
potentially occurring in
the nearby creek. Additionally, migratory birds and other sensitive species that
have a low potential for
occurring in the area were identified and discussed in the M&A study. (See DEIR
page 7-50, Figures 7-2
through 7-5 for known species locations). Lastly, the General Plan 2020 contains
several polices for
protection of environmental resources that were considered in the DEIR analysis,
including CON-1,
CON-2, CON-4 through CON 6, CON-9 through CON-11, CON-13 and CON-14.
The project, as designed, provides the minimum required 50-foot setback from
identified wetlands and
recommended 100-feet from creeks (see DEIR page 3-22, Figure 3-3 – Site Plan).
No sensitive plant species would be affected by the project. The DEIR evaluates
the potential impact of project construction
and operation on raptors that may nest in trees, fish species that may occur in
the creek, migratory birds,
and the identified Clapper rails and Clapper rail habitat. Mitigations measures
are recommended to
address potential impacts to sensitive Clapper rail and fish species and habitat
known and anticipated to
occur in the area, as well as other species that although not found still could
occur given that they are
known to occur in the region. The mitigation measures are primarily proposed to
assure that the project
would not affect breeding and/or migratory patterns of protected species.
This has resulted in mitigation measures that:
a) limit construction to occur between July 1 to February 1, with shorter
construction
windows established for pile-driving activities,
b) requires nesting surveys to be conducted prior to construction,
c) establish lighting curfews for outdoor events and general site lighting, and
d) ensure stormwater pollution controls are implemented in compliance with
local, regional and state requirements.
The following mitigation measures were identified to address the potentially
significant Biological Resources impacts:
MM Bio-1a and 1b (Anadromous Fish) reduce potential impacts of the project on
federally listed fish
species to less-than-significant by restricting the timeframe for bridge pile
driving activities, and
requiring a stormwater pollution prevention program and stormwater management
plan to be
prepared (DEIR page 7-62). While the streambed alteration permit would allow
work to start July 15,
mitigation measure Bio-1a further restricts all bridge work to occur between
August 1 and October
15. Pile driving is further not permitted to start before September 1, which
would avoid disturbance to
breeding activities of any anadromous fish species that may be occurring in the
area.
MM Bio-2a through 2e (California Clapper Rail) reduce potential project impacts
on the Clapper rail
and black rail habitat identified on the North Fork of Gallinas Creek by
requiring installation of barrier
fencing (construction and permanent), a permanent conservation area north of the
proposed building
and fields, recommended scheduled levee maintenance timeframes for the area,
adherence to the
construction timeframe limits, and establishing an outdoor event curfew. (DEIR
pages 7-66 thru 7-69)
The construction timeframes in these measures are consistent with MM Bio-1a. The
event curfew,
however, requires that outdoor events end by 10PM to mitigate noise, which is up
to 2 hours earlier
than proposed by the applicant (see DEIR page 3-13, Table 3-1).
MM Bio-3a and 3b establish lighting controls and a lighting curfew to ensure
nighttime light and glare
would avoid causing significant adverse impacts on adjacent habitat and
nocturnal wildlife movement
(DEIR page 7-70). Measure MM Bio-3b mirrors the 10PM event curfew established
under MM Bio-2.
MM Bio-4a through 4c (Nesting Raptors) reduce the potential impacts that
construction of the bridge
and facility could have on nesting raptors by limiting construction to the
“avoidance window” specified
under MM Bio-1 (although the recreational facility may begin work as early as
July 1), and requiring
16 of 28
preconstruction surveys a minimum of 30 days before commencement of work. (DEIR
pages 7-71
and 7-72).
MM Bio-5 through MM Bio-8 protect against the potential occurrence of other
sensitive species of
concern, which have a low potential for occurring on the site; i.e., the Western
Burrowing Owl,
Common and Special-Status Nesting Birds, Salt Marsh Harvest Mouse, Suisun shrew
and San Pablo
vole, and Pallid and other Bat species. Pre-construction surveys are required to
assure any potential
impacts would not occur as a result of occurrence of these species (which have
not been identified
on-site, but are anticipated in the area), with the appropriate performance
based measures identified
in the unlikely event that a discovery of one or more of these species is made.
(DEIR pages 7-73
through 7-80).
MM Bio-9 is required to assure implementation of all streambed alteration
agreement requirements
would be satisfied for the bridge replacement work (DEIR page 7-81).
In response to comments on the DEIR, Master Responses 5 through 10 (BIO-1 to
BIO-6) expand and
clarify the restrictions that have been established for construction timeframes,
the preconstruction
nesting survey and monitoring requirements, and the fencing and lighting
requirements recommended for
the protection of wildlife species that have been found or anticipated to occur
near the site. These Master
Responses confirm the DEIR conclusions that the project, with the recommended
mitigation measures,
would have less-than-significant environmental impacts.
Minor revisions have been made to the Biological Resources discussion in this
section, as reflected on
FEIR pages R-1 through R-21. These revisions consist of minor corrections and
clarification made to
discussion in the DEIR, which have been based upon the supporting project
studies contained in the
DEIR Appendix E. Revisions have similarly been made to the mitigation measures
in FEIR Chapter 2,
revised Table 2-1, which more accurately describe the necessary construction
time constraints and the
project monitoring requirements. None of the changes are substantive. No new
significant unavoidable
impacts or new mitigation measures would result.
Cultural and Historic Resources (Chapter 8, DEIR pages 8-1 through 8-16)
A study of cultural resources was conducted by Richard Greene, Archaeological
Resource Service, and
is contained in DEIR Appendix F. Review of historic mapping shows the project
area was once part of
the San Pablo bay marsh system and was regularly inundated by tidal action,
until levees were
constructed around the area for agricultural purposes during the 1940’s. In
general terms, a project
impact would be potentially significant if it would cause a substantial adverse
change or result in loss or
destruction of a culturally or historically significant resource.
The site is not historically significant. The likelihood of finding any
prehistoric, archaeological, or historic
resources is considered low given the historic characteristics of the site;
i.e., tidally influenced lands,
placement of fill and prior agricultural use. Regardless, the potential for
uncovering unidentified cultural
resources is presumed to exist in the region. Standard mitigation measures found
in the CEQA
Guidelines have been recommended to guard against the potential that resources
could be discovered
during site grading.
The following mitigation measures were identified to address potentially
significant
Cultural and Historic Resources impacts:
MM CR-1 applies the standard CEQA mitigation which requires monitoring by a
qualified
archaeological professional during any earth moving activities, and establishes
protocols in the event
a discovery of remains (human or artifact) is made.
17 of 28
No significant comments on the DEIR analysis of this topic were made. Thus,
there have been no
revisions required in the FEIR. The project would implement standard mitigation
measures consistent
with CEQA Guidelines to protect against accidental discovery during site work.
Geology and Soils (Chapter 9, DEIR pages 9-1 through 9-34)
The DEIR Geology and Soils analysis relies on the geotechnical reports prepared
by John C Homs &
Associates and City-initiated peer review by Kleinfelder, which is consistent
with the General Plan 2020
geotechnical review matrix. San Rafael does not have any known active fault
traces, but is located
between the Rodgers Creek Fault 5 miles to the east, and the San Andreas Fault
16 miles to the west
(see DEIR Figure 9-1). The geotechnical reports have shown that the site is
comprised primarily of silty
clay soils and silty clay bay mud. In general terms, the project’s impacts would
be potentially significant if
it would destroy a unique landform, expose people or structures to hazards
including unstable soils,
cause significant erosion, destroy a mineral resource or contribute to any
geological, soils or seismicity
impact.
The DEIR concludes that the potential for ground rupture is low given that there
are no fault traces on the
site. The fill soils over bay mud are not identified as susceptible to
liquefaction. Earthquake resistant
construction in compliance with the California Building Code is required to
assure ground shaking
impacts are mitigated.
Given the special characteristics of the site, being comprised of fill over bay
mud,
foundation systems are limited to use of engineered designs. This requires:
a) conducting detailed soils analysis for the site;
b) design of graded slopes and systems to carry drainage away from structures,
and;
c) use of concrete or steel driven piles in-lieu of conventional slab on grade.
Therefore, the following required mitigation has been required to ensure impacts
would remain less-than-significant.
MM Geo-1 is being required to assure the recommendations of the geotechnical
report are
implemented at the time of construction. This includes the use of driven piles
to bedrock to support
the buildings, hinged slab for site work and flexible utility connections to
accommodate anticipated
level of differential site settlement.
There have been no changes made to the DEIR in response to comments in this
category. Comments
were submitted concerning the safety of the levee, including construction and
maintenance. In order to
respond to the DEIR comments on issues in this section, staff required that an
additional investigation of
the levee and site be conducted to confirm the assumed integrity of the levee
and depth of bay mud
onsite. This further investigation is contained in FEIR Appendix B. Questa
Engineering Corporation was
hired to provide further peer review of the levee safety and potential flooding
risk analysis prepared for
the project. The FEIR Master Responses 12 and 13 and FEIR Appendix B confirm the
conclusions of the
DEIR regarding stability of the levee and that the levee fill has completed full
compaction.
The levee ownership and maintenance obligations and practices of the airport
property owner and Marin
County flood control staff have also been further identified (see FEIR Figure 3,
page C&R-29). The levee
would continue to be annually inspected by the airport owners and Marin County,
with repairs and fill
added to maintain the 9-foot height. The County has stated that they are not
interested in entering into a
formal maintenance agreement for this levee system. This issue was explored to
some extent by County
staff. However, the levee is not engineered to flood control district
specifications, and is not in a flood
control district. If the County were to enter into a formal maintenance
agreement with the property owner,
the County could be held liable for the condition and repair of the levee.
Therefore, the County staff
would continue their own periodic review and maintenance practices. Likewise,
the property owner would
continue their routine maintenance practices, which consist of periodic
inspection of the levee and adding
additional fill soils to the tops of the levees to fill holes and maintain its
9-foot height. City grading permits
may be required for significant fill amounts in excess of 50 cubic yards.
18 of 28
Lastly, the building would be constructed on suitable pile foundations and
flood-proofed at +7NGVD
elevation in compliance with FEMA requirements, to assure that water would not
penetrate the building in
the event flooding occurs as a result of seismically induced levee failure. John
C Hom & Associates
analysis has confirmed that piles for the building could be driven down to
bedrock (see FEIR Appendix B,
Log of Boring 1; which shows bedrock depth of 44-feet). Thus, no seismic-related
structural hazards
have been identified that cannot be adequately addressed and mitigated.
Hazards (Chapter 10, DEIR pages 10-1 through 10-26)
This section of the DEIR evaluates the project in context of safety and
environmental hazards that may
be present on-site and that the project may pose to others. An aeronautical
safety review was prepared
by Mead & Hunt, aeronautical consultants (DEIR Appendix H). The airport hazards
study evaluated both
safety on the ground for occupants of the facility and safety of aircraft as a
result of placement of the
building near the runway. A review of local and state lists of hazardous waste
sites was also conducted,
and also provided in DEIR Appendix H, to assess impacts from exposure to
hazardous substances.
The airport is identified as having 15,000 annual, private small aircraft trips
(7,500 takeoffs and 7,500
landings) on the single airport runway, and does not have an air traffic control
operator (required for
commercial airports). This equates to the roughly 20 takeoffs/20landings per day
reported elsewhere in
this report. The study notes that the private airport facility is limited by the
City use permit to no more
than 100 aircraft, with small planes, not exceeding 15,000 flights annually
(takeoffs and landings); with
the majority (85%) off aircraft operations occurring during daylight hours. This
continued level of
operation is expected to remain essentially unchanged. Aircraft typically
arrive/depart east of the airport
and runway over the baylands, and west to/from 101 when winds are from the west,
avoiding overflight of
residential neighborhoods. The pilot is ultimately responsible for determining
the safest direction for
departure/landing based on conditions.
The FAA establishes a 125 foot development setback (aviation clear zone) from
the centerline of the
runway for the small private airport facility. The FAA establishes transition
zones adjacent to the runway
approach and landing strip that must be kept clear of obstructions in order for
aircraft to safely
descend/ascend to/from the facility. The airport safety study identifies basic
safety zones that would
apply to project land uses around the runway, outside of the aviation clear
zone, using the California
Airport Land Use Planning Handbook, published by the California Department of
Transportation Division
of Aeronautics†. The recreational facility is located in Zone 5 – Sideline Zone,
which encompasses the
close-in area lateral to the runway which is not normally overflown and has a
low risk of an aircraft
accident. The outdoor warm-up field is proposed within Zone 2 – Sideline Zone,
which is an area
overflown by aircraft at low altitudes (closer to the end of the runway) and
considered to be exposed to
substantial risk. The safety study estimated a peak intensity of 475 people
would be on the recreational
facility site using the facilities (Mead & Hunt, page 7). The project would have
a potential significant
impact if the activity would conflict with airport operations, or exceed the
thresholds for activity within the
safety zones identified in the airport hazards study. DEIR Figures 10-1 and
Figure 10-2 show the airport
layout and safety zones.
† The DOT Handbook website states its purpose is to support and amplify the
article of the State Aeronautics Act
(California Public Utilities Code, Section 21670 et seq.) which establishes
statewide requirements for the conduct of
airport land use compatibility planning. The Handbook provides compatibility
planning guidance to airport land use
commissions (ALUC’s), their staff, consultants, and the counties and cities
having jurisdiction over land use
surrounding airports. http://www.dot.ca.gov/hq/planning/aeronaut/handbook2011.html
19 of 28
It has been established that the building would contain high risk users, such as
elderly and youths, that
could have difficulty leaving the facility in the event of an emergency. Also,
improvements on-site could
minimally encroach within the airspace required to be kept clear for aircraft,
per FAA standards. Thus,
any safety thresholds that are exceeded would need to be mitigated. In addition
to airport related
hazards, potential impacts would result if a project would create objectionable
odors affecting a
substantial population, or would be located on a site containing hazardous
materials, or in close proximity
to a hazardous waste site.
The following project Hazards impacts have been identified and discussed:
Exposure to Hazardous Materials and Substances
There are no known sources of contamination on the project site. Review of
historic aerials and
information do not show any historic uses on the project site that could have
resulted in contamination,
prior to use of the site for agricultural purposes circa 1915 or installation of
levees in the 1940’s. There
are no toxic waste sites or waste generators located in the area, as indicated
in DEIR Appendix H, which
includes a review of the State Department of Toxic Substances Envirostar
Database. The site is also not
on a list of hazardous materials site maintained by the San Rafael Fire
Department.
Airport Safety Hazards to People
The airport safety study concludes that buildings “provide substantial
protection from the crash of a small
airplane” (DEIR, Appendix H, page 5 of the Aeronautical Safety Review).
Special risk-reduction construction features that could be required to mitigate
the potential for an aircraft accident to occur on
the project site include:
• single story wall height;
• concrete walls,
• upgraded roof strength,
• limited number of windows,
• no skylights,
• enhanced fire sprinkler system (designed in a manner that the entire system
would not be disabled by an accident affecting one area), and increased number
of emergency exists beyond California Building Code (CBC) requirements.
The airport safety study establishes an average threshold of 100 people per acre
as being an acceptable
safety threshold within the project site area, north of the runway.
Concentrations of people over 200
people per acre would be considered potentially significant. The report
concludes the 1.6-acre
recreational building would have the greatest concentration of people, and that
the anticipated
occupancy amount would slightly exceed the 200 people per single-acre intensity
threshold established
for Zone 5. Therefore, special risk-reduction design building features must be
incorporated to mitigate
this level of impact. The risk-reduction design features that are required to
mitigate exceedance of the
single-acre intensity threshold within the building include provision of
enhanced fire sprinkler systems
and increased emergency exits for the building.
The outdoor warm-up field located in Zone 2 could potentially exceed the average
100-person per acre
intensity threshold, which would be significant given the increased risks
associated with this area. In
order to reduce the risk, it is recommended that the occupancy of this area be
limited to 50 occupants,
maximum. This limitation is reasonably enforceable with signage and would not be
likely exceeded given
the fact that it would be used at most by 2 soccer
teams awaiting games on the outdoor field.
Several comments on the DEIR raised questions regarding how the maximum
single-acre intensity
occupancy calculation was determined for the airport hazards analysis, which
states that intensity of use
would slightly exceed the recommended 200 people per single-acre intensity
threshold. In response to
comments, Master Response 1 (PD-1) clarifies how this intensity calculation was
determined. The
occupancy calculation is based on the anticipated concentration of people within
airport basic safety
zones. i.e., inside the recreational facility building, outside the building and
on the outdoor soccer field
within basic safety zone 5, and on the outdoor warm-up field within basic safety
zone 2 (see DEIR Figure
20 of 28
10-1 and Plan Sheets A-2 and A-5 for the location of safety zones and the 7:1
‘ascending clear zone’
transitional surfaces).
The highest occupancy for the site would occur within the building, which has a
development footprint
covering up to 1.6 acres of the site. The occupancy calculated for the indoor
facility of 216 occupants
was determined based on the highest occupancy level anticipated for the
recreational facility building.
The assumptions used to determine this occupancy amount have been confirmed as
compatible with the
CBC methodology for calculating the maximum allowable occupancy for generally
assembly use, and the
traffic study methodologies used for calculating the projects trip generation.
The occupancy level
assumed by Mead & Hunt for the recreational building’s gymnasiums, indoor fields
and indoor
mezzanine were assumed at 50-percent of the CBC maximum occupancy allowance for
general
assembly usage. Mead & Hunt considers its assumptions on occupancy to be
conservative for the
recreational facility use, on the basis that industry surveys conducted of
actual occupancy levels indicate
that many uses are generally occupied at no more than 50-percent of CBC maximum
occupancy levels,
and the recreation facility building is not proposed to be used for higher
occupancy general assembly
uses; e.g. fixed or general seating for stage/theater and auditorium uses.
Airport Safety Hazards to Flight
Based on review of project plans, the Mead & Hunt concluded that portions of
parked cars, proposed
fencing, trees, lighting and building corners could slightly encroach (by an
amount of less than 2-feet)
within the 7:1 ‘ascending clear zone’ that is required for aircraft to safely
transition to/from the runway;
shown on DEIR Figure’s 3-4 and 3-7 (Plan Sheet’s A-2 and A-5). The potential
encroachment locations
are shown on DEIR Figure 10-2. These assumed encroachments result from an
assumption that the
runway grade is slightly lower than actual. The following mitigation measures
would address the
potentially significant single-acre intensity occupancy and potential structure
encroachment impacts:
MM Haz-1 and MM Haz-2 are recommended to reduce potential impacts to site
occupants and flights
by requiring upgrades to building exiting and fire sprinkler systems, signage to
restrict occupancy of
the warm up field to 50 people, and limiting height of buildings and features to
assure clearance of
the ascending clear zone is achieved. The measures may require slight
modifications to lower height
of the building, parking area and related improvements by 0.5 to 1.7-feet,
and/or install obstruction
lights at the affected locations (DEIR pages 10-20 and 10-25).
Due to the fact that the building would have high risk users, the Aeronautical
Safety Review (Mead &
Hunt, DEIR Appendix H) confirms that the project can incorporate specific risk
reduction design features
to mitigate its potential exceed the single-acre intensity threshold. Although
the report identifies several
risk reduction design features that could be used, it recommends the specific
features that should be
required for the impact of this project (page 10 of the Aeronautical Safety
Review). All risk reduction
features are not required to be implemented. The minimum features deemed
necessary for the building
include installation of enhanced fire safety and exiting for the building. The
mitigation measures reflected
in MM Haz-1 and MM Haz-2 implement the safety study recommendations, and would
adequately
mitigate the slight exceedance of the single acre intensity threshold and
potential encroachments into
ascending clear zone space.
Hydrology and Water Quality (Chapter 11, DEIR pages 11-1 through 11-36)
Oberkamper & Associates prepared a hydrologic analysis, which included
evaluation of drainage (runoff
increases, volume and velocity) and potential for levee breach (see DEIR
Appendix I). The flat site is
located in low lying baylands protected by levees. The analysis analyzes the
addition of 4.6 acres of
hardscape from the recreational facility project that is proposed to be added to
16 acres of existing site
21 of 28
development, located within the projects 106 acre watershed area. This new
hardscape area would
result in a 1/8th inch increase in the depth of water during a 100 year storm
event. The additional amount
of runoff created by the project is relatively minimal, and would have an
insignificant effect on the
hydrologic and hydraulic conditions. The site would drain into the man-made
drainage swales located on
the north and south side of the building, and empty into the creek via an
existing pump-station. The
volume of water added to this watershed would easily be accommodated by the
existing holding capacity
of the site, and the capacity of the pump station to eject 500,000 gallons per
hour/18.5 cubic feet per
second from the site into the creek. Impacts would be potentially significant if
runoff would violate water
quality standards, substantially alter drainage patterns, degrade water quality,
or expose people or
structures to loss or damage from flooding.
Construction activities would potentially impact water quality. Runoff over the
parking lot could carry
contaminants to the waterway. Increasing runoff discharge into the creek could
have a cumulative impact
on water quality. Lastly, a breach of the 9-foot tall levees that surround the
site could result in flooding of
the site (which lies below the +6 NGVD flood elevation). A levee breach would
affect the structure and its
occupants. The February 24, 2006 levee breach analysis by Oberkamper and
Associates is provided at
after the Hydrologic Analysis in DEIR Appendix I. This is followed by a February
24, 2006 analysis of the
low potential for levee failure due to liquefaction, prepared by John C Hom that
has been further
confirmed in the study attached as FEIR Appendix B. The hydrologic analysis
assumes a conservative
scenario of an instantaneous 100-foot wide levee breach down to +3NGVD
elevation, with breach
reaching a width of 325 feet as flood waters enter the site, and erosive
characteristics reduce as flood
waters achieve +3 foot elevation. This analysis was based upon a 400 foot wide
breach which occurred
in the delta in June 2004. The analysis concludes that flood waters would reach
an elevation of +2 feet in
2 hours and 15 minutes, and provide ample time for occupants to leave the
facility. Further discussion of
potential impacts of levee breach and sea level rise are provided in the Climate
Change discussion
below. The following measures have been identified to reduce the potential water
quality and flooding
impacts to less-than-significant levels.
MM Hyd-1a through f require plans to be submitted with building permits that
would assure erosion,
siltation and water runoff will be treated to avoid contaminating the waterway.
This will include
providing enhanced grassed swales to filter pollutants from runoff, preparing
stormwater pollution
prevention and stormwater management plans (SWPPP, SWMP) and maintaining paved
areas clear of
debris for the duration of the project use (DEIR pages 11-23 through 11-25).
MM Hyd-2a and 2b require the building to be flood proofed and watertight to an
elevation of +7 feet
NGVD so that it is impermeable to penetration of water, and specifying criteria
for finalizing hydrology
and grading plans to support final design of improvement plans (DEIR pages 11-32
and 11-33).
There were several comments received for this DEIR topic area. Master Responses
11 through 14
(HYD-1 through HYD-4) provide updated FEMA flood elevation datum values (to
illustrate the change
from the 1929 NGVD to current NAVD)‡ and further characterize the potential
impacts of sea level rise
and potential flooding impacts. Master Response 15 (HYD-5) further addresses
water quality impacts.
Minor revisions to the FEIR discussion have been provided to this section, which
can be found on FEIR
pages R-7 and R-10. These revisions are reflected in revised Mitigation Measure
MM Hyd-1a which has
been amended to clarify the erosion control requirements that would apply to the
project as part of its
construction, and revised MM Hyd-2a which has been modified to indicate the new
flood elevation datum
values (as reflected in revised FEIR Table 2-1). The FEIR responses conclude
that no additional
hydrology or flooding impacts would result.
‡ The change from the 1929 NGVD to more recent NAVD results in a +2.67 increase
in the datum value but this
does not reflect change in site hydrology. In this report, staff has continued
to use the old 1929 NGVD datum value
for reference, in order to avoid confusion from switching between NGVD and NAVD
datum values.
22 of 28
Noise (Chapter 12, DEIR pages 12-1 through 12-26)
DEIR Appendix J contains the noise study prepared by Illingworth & Rodkin. A
peer review of this noise
study was completed by Geir and Geir. The analyses assessed existing noise
conditions, which primarily
result from airport use. Project-generated noise was found to be primarily
attributed to the increased
vehicle traffic traveling to and from the facility, and from the games on the
outdoor field. Construction
noise impacts were also evaluated, as a result of construction vehicle and
equipment operation, and pile
driving activities. McInnis Park is located within 300-feet of the site. Santa
Venetia residential
neighborhood is located within 750 feet to the south of the outdoor warm up
field and Contempo Marin
residential neighborhood is located 1,000 feet from the recreation building.
Contempo Marin is separated
from the airport site by a solid block wall, and existing airport hangar
buildings. The access driveway runs
along the boundary of Contempo Marin and Captains Cove residential
neighborhoods. There are no
walls or structures directly between the homes in Captains Cove and the site
access road. No other
noise sensitive land uses are in close distance to the facility. A noise impact
would be significant if the
project increases noise levels noise-sensitive receptors exceeding thresholds,
and if construction created
significant ground-bourne vibrations. The intermittent high noise levels
generated by aircraft takeoffs is
not deemed significant to the outdoor fields use. The following noise related
impacts have been
discussed in the DEIR:
Construction Noise
The analysis has concluded that the high decibel noise generated by construction
vehicles and pile
driving activity may also disrupt field use at McInnis Park. Mitigation has been
required as noted below.
Traffic Noise
Traffic noise would be significant if it would increase levels at noise
sensitive receptors by 3 decibels, if
existing noise exceeds 65 dBA. The project does not exceed the established
threshold.
Operational Noise
The noise analysis for the DEIR has identified that games on the outdoor soccer
field could generate
increased noise levels at the nearest residential property line in Santa
Venetia, which may result in a 1
decibel exceedance of the 40 dBA Ldn (nighttime) threshold established by the
City Noise Ordinance
(Chapter 8.13). Chapter 8.13 defines nighttime hours as the periods between 9PM
and 7AM Sunday
through Thursday, and between 10PM and 7AM Friday and Saturday. The City noise
ordinance
establishes a much more stringent outdoor residential noise threshold for
properties within the City;
whereas the General Plan 2020 Policy N-1, Exhibit 31, establishes 40dBA as the
upper range of
normally acceptable interior residential exposure limit and 60dBA as the upper
range for normally
acceptable exterior residential exposure limit. The noise limits in the General
Plan are the more common
residential noise thresholds. However, for purposes of environmental review the
City Noise Ordinance
requirements have been applied to all surrounding residential properties
including Santa Venetia, which
is outside the City Limits and is not subject to the City’s Noise Ordinance.
Monitoring of the use has been
recommended to determine whether anticipated noise levels would actually exceed
the City noise
threshold at the nearest residential property line. If this is the case, the use
of outdoor fields would be
required to cease by 9PM on weekdays.
The following mitigation measures would reduce operational and construction
noise impacts to less-thansignificant
levels:
23 of 28
MM N-1 requires outdoor field use to be monitored by a noise consultant during
the first year of use
to determine whether nighttime games would cause the City Noise Ordinance to be
exceeded at the
nearest residential property line. If noise ordinance would be exceeded, 9PM
would be set as the
curfew for the outdoor field use on weekdays (DEIR page 12-21).
MM N-2 and MM N-3 address the construction noise impacts through assuring
construction vehicles
are maintained and operated appropriately and requiring pre-drilling of holes to
shorten the duration
of pile driving (DEIR pages 12-24 and 12-25).
Master Responses 16 and 17 provide further clarification of the DEIR noise
analysis discussion, in
response to comments regarding the nighttime noise and intermittent noise levels
anticipated from
outdoor field use. As a result of further review of outdoor noise impacts,
Mitigation measure MM N-1 has
been modified to eliminate a proposed sound wall as an option for reducing noise
levels; which was
identified to allow game times into the nighttime hours on weekdays to extend
slightly longer, from 9PM
to until 10PM. Rather, the mitigation measure has been modified to require
monitoring of games during
the first year of operation to determine whether the established noise
thresholds would be exceeded
during this 1 hour period. Additionally, MM N-2 regarding construction time
restrictions has been
appended to further assure that construction activities would avoid causing
conflicts with daytime usage
of the nearby field at McInnis Park.
Transportation and Traffic (Chapter 13, DEIR pages 13-1 through 13-44)
The traffic analysis for the project was prepared by Fehr and Peers,
transportation consultants, and is
contained in Appendix K. The study evaluated the five signal-controlled
intersections that would be would
affected by project traffic along the Smith Ranch Road/Lucas Valley arterial (DEIR
Figure 13-1). The
study also assessed the Yosemite Rd and Silveira/Smith Ranch intersections to
determine if signal
warrants would be met, to require installation of additional traffic controls at
these locations. (Appendix K
- Attachment A). A study of arterial segments was provided to determine whether
the project traffic
would result in any significant delays along the roadway. This was primarily
conducted as a means of
confirming queuing capacity between signalized intersections was adequate.
However, the arterial
segment identified in the General Plan requires Smith Ranch Road/Lucas Valley
Road to be split due to
the change in roadway name, whereas this is a continuous segment. Thus, arterial
segment level of
service is not a good standard for evaluating traffic operations in this area.
Intersection LOS has been
maintained as the appropriate standard to be used for the roadways and
intersections impacted by
project traffic. The DEIR identifies the following conditions: baseline traffic,
baseline with project, general
plan, and general plan with project. The analysis also discusses the proposed
site access, pedestrian
and alternative transportation modes, transit, and parking facilities.
The General Plan 2020 establishes a level of service standard D for
intersections within the project study
area. An impact would be significant if it would cause the level of service
standard to be reduced from an
LOS D condition to an LOS E condition from the addition of project traffic, or
add traffic to an existing
intersection that currently operates below the LOS D standard during the peak
hours of intersection
operations. The peak hours are the periods of 7AM to 9AM and 4PM to 6PM. The
project generates 268
PM peak hour trips, with 135 trips in and 133 trips out (DEIR Table 13-3). Based
on distribution and
assignment of these vehicle trips, it was concluded that the project would not
cause the LOS D threshold
to be exceeded at the intersections impacted by the project. Additionally, the
project would be required to
pay its fair share of traffic mitigation fees, in the amount of $1,137,926.00,
which would be used to fund
the traffic improvements that have been identified by the General Plan 2020 for
cumulative development.
As this traffic mitigation fee has been established and is required citywide, it
is imposed as a condition of
project approval in-lieu of a mitigation measure. In addition, the signal
warrants were not met at nonsignalized
intersections evaluated along Smith Ranch Road (DEIR Appendix K). It has been
concluded
24 of 28
that the existing non-signalized intersections would continue to function
adequately without a significant
increase in delays or concerns with adequate vehicle sight distance before
making turns onto Smith
Ranch Road.
The DEIR analysis had also concluded that short-term vehicle queuing before
dance and gymnastics
classes could cause vehicles to backup at the bridge deck. This was concluded to
be the case if the
existing single-lane bridge deck were to remain. However, the project does
include replacement of the
deck with a wider 2-lane roadway surface. Therefore, Mitigation Measure Traf-1
has been deleted due to
the fact that the project includes installation of a new two-lane bridge deck
and the queuing impacts
previously anticipated on the private road adjacent to residential uses would
not result.
Several comments were submitted questioning why the non-signalized intersections
along Smith Ranch
Road were not evaluated in the traffic study, why the analysis was not conducted
when McInnis field was
active, and the impact of SMART operations. Master Responses 18 and 19 (TRA-1
and TRA-2) include a
revision to the impact analysis discussion in the DEIR to clarify that the City
significance threshold for
AM/PM peak hour traffic (General Plan Policy C-5A) applies only to signalized
intersections along the
Smith Ranch Road and Lucas Valley Road segment that would be affected by project
generated traffic.
Arterial segment LOS is not the threshold that applies for this location.
Further, the traffic study evaluated
the peak weekday traffic conditions, which reflects the most significant period
of traffic at these
intersections. FEIR pages R-26 through R-33 include revisions to the discussion
in DEIR Chapter 13,
which clarify that signalized intersection level of service LOS D is the
threshold used by the City for
analysis of project impacts. Finally, as discussed in paragraph 3 of this
section above, the analysis
evaluated the unsignalized intersections along Smith Ranch Road to determine
whether warrants would
be met for installation of traffic controls, and these intersections did not
meet the warrants. Thus, the
traffic related impacts on Smith Ranch Road would be less-than-significant for
purposes of environmental
review.
Master Response 20 (TRA-3) responds to comments on the impact of SMART train
operations. This
topic has been fully evaluated in a certified EIR prepared for the SMART
project. SMART has over 100
crossings that it must address, and has identified several crossing control
options. SMART would result
in relatively rapid pass-bys and would not result in any significant delays for
vehicles entering or
departing form the site at the at-grade crossing located at the airport site
boundary. Thus, no significant
impacts would result from SMART train operations.
Other Environmental Effects (Chapter 14, DEIR pages 14-1 through 14-16)
Study areas in the DEIR that result in either a No Impact conclusion, or that
did not require mitigation
measures include Agricultural Resources, Mineral Resources, Population &
Housing, Public Services,
Recreation, Utilities & Services, Cumulative impacts, and Growth Inducing impact
categories. The project
has not resulted in potentially significant impacts in these categories;
therefore, no mitigation measures
have been required.
Master Response 21 (GI-1) has been provided in response to comments, to confirm
that the project
would not have any growth inducing impacts. The project is limited by existing
utility service agreements,
and would not require upgrades to existing public utility systems or public
infrastructure in order to
accommodate the increased development on site.
Chapter 14 Cumulative Impacts discussion has been revised to incorporate all
cumulative impact
discussion in a single chapter (See FEIR Chapter 2: Revisions, pages R-33 to
R-42). No new significant
unavoidable impacts or mitigation measures have been identified as a result of
the FEIR response to
comments in this Chapter.
25 of 28
Climate Change (Chapter 15, DEIR pages 15-1 through 15-16)
SB97 (Greenhouse Gas Emissions) and AB32 (Global Warming Solutions Act), were
enacted during
preparation of this EIR. The contribution of a local project to global
environmental warming is considered
too be speculative, and no thresholds had been established by the state at time
of preparation of the
DEIR that could have been used to evaluate or measure global warming impacts at
a local project level.
The DEIR provides a general response identifying the methods by which the
project may control its
contribution to greenhouse gas (GHG) emissions through implementing some
practicable available
control measures. In addition, the potential affect of global warming on the
project locally is also
discussed; such as impact of potential sea level rise.
Sea Level Rise
Master Response 22 (GHG) has been prepared to respond to concerns raised
regarding sea level rise
and greenhouse gas emissions assessment. These are global areas of concern that
were developing
during preparation of the EIR. Sea level rise may occur as a result of global
warming, which could
potentially affect the project site and all low lying areas protected by levee
systems. This is beyond the
project scope, and such an impact if realized would need to be addressed on a
regional basis. FEMA has
been updating flood maps to address new mapping standards, and would be
responsible for evaluating
this regional impact. As designed, the building would be flood proofed to
protect against flooding as
required by FEMA. The existing 9-foot tall levee has been analyzed and found to
be adequate to
continue protecting the site through the year 2050 in the event that the current
estimates of an 18-inch
sea level rise were to be realized. The creek elevation is approximately +3 feet
NGVD. The 100 year
flood elevation of the creek would rise to +6 feet NGVD (during period of high
tide with stacking of flood
waters). A levee breach would typically occur due to erosion of the levee caused
by water cresting the
levee during a 100-year storm. Surcharge of waters against the levee walls is
not a risk factor. The
earthen levee has achieved full compaction since its construction in the 1940’s
and, as a result, is
considered to be sound and not subject to liquefaction. The levee has not failed
during recent
earthquakes (including Loma Prieta) and if it is continued to be properly
maintained at its current
elevation, through routine filling of low points that may occur in the levee
system, it is not anticipated to
be susceptible to failure due to a levee breach. Furthermore, the levee height
may be increased over
time through the addition of soils, which would be compacted onto the top of the
levee. Therefore, the
project would not be subject to any significant Climate Change impacts as a
result of sea level rise, and
no mitigation measures are required.
Global Warming/Greenhouse Gas
DEIR Chapter 15 has been augmented to clarify the threshold for analysis in the
DEIR is based on
whether the project would conflict with AB 32 (Global Warming Solutions Act),
and incorporate the
information regarding the measures available to reduce project related GHG
emissions (FEIR pages R-
42 through R-46 and Master Response 22; GHG-1). However, staff has also included
a more up to date
quantitative analysis showing level of project conformance with the Bay Area Air
Quality Management
District (BAAQMD) newly adopted thresholds of significance. Analysis based on
this standard is not
required, but has been provided for informational purposes in Master Response
22. This additional
analysis shows that due to the fact that all vehicle miles traveled (VMT)
attributed to the project are
treated as new regional trips, which are primary source of its greenhouse gas (GHG)
emissions, it would
not be possible for the project to reduce its emissions below the new BAAQMD
significance threshold of
1,100 metric tons of greenhouse gas emissions annually (MT/CO2e).
26 of 28
Master Response 22 clarifies that the threshold of significance used for this
project is whether the project
would impede the Global Warming Solutions Act (AB32). FEIR Table 1 on page
C&R-45 identifies the
applicable qualitative standards used to evaluate project conformance with
strategies for reducing
greenhouse gas emissions. While many of these are related to improvements
required for vehicles, there
are several strategies that encourage green building construction and water
conservation. As noted
above, at the time of the publication of this report, there was no state adopted
method for assessing a
local projects impact on global warming. It is reasonable to anticipate that the
project would be affected
by state and federal mandates requiring improved vehicle and equipment energy
efficiency; at time of
construction or replacement of vehicles or equipment. The project must also
comply with updated Title
24 mandates and meet all other applicable standards and regulations addressing
energy and building
efficiency. Further, although the project is exempt from the City’s local green
building ordinance, the
project proposes to achieve US Green Building Council LEED certification which
would lessen the project
impacts. This includes installation of rooftop solar, energy efficient lighting
systems, use of recycled
water if available, and installation of all-weather field turf (reducing energy
for water transmission and
maintenance). These efforts would reduce greenhouse gas emissions through
reduction in the project’s
demand on nonrenewable energy usage. Thus, the project would not impede
implementation of AB 32
and would not result in significant impacts using this applicable threshold.
Since publication of the DEIR, the Bay Area Air Quality Management District (BAAQMD)
adopted new
thresholds of significance on June 2, 2010 that provide a qualitative method for
evaluating greenhouse
gas emissions. Although analysis based on this standard is not required, staff
has provided this analysis
on pages R-44 & R-45 and Master Response 22 beginning on page C&R-43. This
analysis concludes
that the project would generate 2,203 metric tons (MT/CO2e) annually as a result
of increased vehicle
traffic, which would exceed the new BAAQMD significance threshold of 1,100
metric tons (MT/CO2e)
annually. The project includes green building techniques that would reduce its
emissions by
approximately 386 metric tons of CO2e emissions. However, due to the isolated
geographic location and
lack of multi-modal transportation opportunities the project cannot
significantly reduce the amount of
vehicle miles traveled (VMT) attributed to the project, which is the primary
source of its GHG emissions.
Although the project is not required to meet this new threshold, it is worth
noting that the VMT attributed
to the project would likely be similar to another location in Marin County and
further the analysis assumes
the facility would generate new regional VMT, which may or may not be true.
Alternatives (Chapter 16, DEIR pages 16-1 through 16-28)
As required by California Environmental Quality Act (CEQA) Guidelines Section
15126.6, the DEIR
considered and analyzed a reasonable range of feasible alternatives that would
lessen impacts and meet
basic project objectives. The DEIR assessed the following three alternatives:
• No Project
• Reduced Development Intensity
• Alternative Location
The No Project alternative would maintain the existing airport operation, as
regulated under the existing
Master Use Permit with 100-based aircraft and 12 non-aviation businesses
operating between the hours
of 7AM to 6PM. Private and public recreational uses would also remain a
potential use consistent with
the December 1983 property restrictions. This scenario would not include a
recreation building and
associated indoor uses. Without building or bridgework construction, the
comparative analysis of this
scenario identifies that impacts in biological, geology, hazards, hydrology and
noise would be reduced to
levels below the project. Master responses 23 and 24 (ALT) expands the No
Project alternative
discussion to include a No Project / No Build variant (see also Chapter 2:
Revisions Page R-46 to R-50).
This additional discussion does not identify any additional impacts or
mitigation measures. Rather, it
27 of 28
clarifies that the no development option would not result in any of the
associated traffic, biological, noise
or lighting impacts identified in the document.
The Reduced Development Intensity alternative retains the existing single-lane
bridge deck, eliminates
nighttime lighting and use of outdoor fields, and assumes a smaller indoor
sports facility by eliminating
the two court uses. The comparative analysis of this alternative identifies that
impacts in biological,
hazards and noise would be reduced to levels below the project. Finally, the
Alternative Location analysis
concludes that an alternative site within the City would require similar level
of analysis, generating similar
traffic and cumulative impacts. Given that this project results in mitigation of
all environmental impacts,
an alternative location would not necessarily achieve greater environmental
protection.
Thus, the FEIR has provided discussion of a reasonable range of alternatives to
the Project, as required
under CEQA. This analysis provides sufficient information to compare impacts of
approving the project
with impacts of not approving the project. As a result of this review, none of
the alternatives would
achieve the project objectives. However, all impacts associated with the
proposed project could be
mitigated to less than significant levels.
FEIR Conclusions
As required by CEQA, all potential environmental impacts of the project would be
mitigated to the extent
feasible. None of the revisions made to the DEIR have resulted in new impacts or
required new
mitigation measures. Thus, recirculation is not required under the requirements
of CEQA Guidelines for
any revisions made to the DEIR discussion and mitigation measures. Further, no
additional public review
and comment period is required for the FEIR. Comments on the FEIR may be
accepted during the
hearing, but do not require an additional written response beyond that already
provided.
A Mitigation Monitoring and Reporting Program (MMRP) would be prepared prior to
project approval, in
order to demonstrate the program to implement all measures required to mitigate
impacts to less-thansignificant
levels. The MMRP would be incorporated into draft conditions of project
approval.
NOTICING/CORRESPONDENCE
At least 15 days prior to the Planning Commission meeting, a public hearing
notice was mailed to
property owners and occupants within at least 1,000 feet of the site as well as
other community groups,
neighborhood associations and interested parties. The entry to the airport site
and the entrance to the
levee trail at McInnis Park site were also posted with public notice hearing
boards, and a notice was
published in the local Marin IJ newspaper. Staff also has emailed notice of the
hearing to interested
parties that have previously provided email addresses. A copy of the public
hearing notice is attached
(Exhibit 3). Comments received since publication and release of the FEIR and
prior to publication of this
report have been attached.
Comments received to date include at least one letter in support of the project,
and several letters
opposed; including continued concerns with noise, a violation of the intent of
the 1983 Declarations of
Restrictions, expressing inadequacy of response to comments on traffic, noise
and lighting impacts,
impacts on habitat and protection, concerns with impaired drivers leaving the
facility, safety from
potential aircraft crashes, among others. A letter has also been received from
the Department of
Transportation requesting further revisions to the traffic impact report, and a
letter from Marin County
Counsel agreeing that the project is not in conflict with the covenant, and
requesting conditions of project
approval to recognize the 1983 Declaration of Restriction and include them on
future project referrals. No
further written response to comments is required. The responses to comments will
be addressed as part
of the staff and the City’s environmental consultant’s presentation to the
Planning Commission.
28 of 28
NEXT STEPS
If the Planning Commission recommends certification of the FEIR, staff would
return with a complete
staff report on the project merits and draft resolutions required to take action
to approve the project.
Should the Commission reject certification of the FEIR, the project could not
proceed unless appealed to
the City Council, or until a revised EIR has been certified.
OPTIONS
The Planning Commission has the following options:
1. Adopt Resolution Recommending that the City Council Certify the EIR and
direct staff to prepare
resolutions with draft CEQA Findings of Fact and MMRP for Project Approval, PD
Rezoning,
Master Use Permit and Environmental and Design Review Permit (staff
recommended);
2. Reject certification of the EIR and direct staff to prepare further revisions
to the response to
comments;
3. Deny certification of the FEIR and direct staff to draft resolutions to deny
the PD Rezoning, and/or
Master Use Permit and Environmental and Design Review; or
4. Continue the matter to future Commission meeting for further review and
discussion.
EXHIBITS
1. Vicinity Map
2. Draft Resolution Recommending California Environmental Quality Act (CEQA)
Certification
3. Public Hearing Notice
4. Recent Correspondence (rec’d since publication of the FEIR)
The following Exhibits have been distributed to the Planning Commission Only:
5. Environmental Impact Report (distributed separately)
6. Project Plans
|