| 
  
   $5.8 bil. for the Bay Bridge &
   
  still pushing a $3 billion Transbay Terminal ? 
  ($3 billion, SO FAR ! ) 
  
  
    
      | 
   The
  East 
  Side 
  of the Bay 
  Bridge is actually
  2 bridges -- nearly two 
  miles of Twin concrete 
  Viaducts reaching west from Oakland and the
  Replacement of the 
  East Span, a 
  single-tower suspension span
  connecting to Yerba Buena Island. Both now 
  totalling $4.4 billion (from $2.6 bil. in 2001), 
  
  
  http://www.donaldmacdonaldarchitects.com/SFOBB/SFOBB_east1.html 
   
  
  "The cost-benefit ratio of the Transbay Terminal is really absurd,"
   said Bill Blackwell, a retired 
  Bechtel architect, 
  who contends that the new terminal costs 
  aren't justified by the improvements for transit riders. "People seem to 
  think we need a new monument," 
  Blackwell said. "We don't need a 
  fancy new terminal. It doesn't do anything to enhance transit use." 
  
  For that kind of money we should be 
  doing SOMETHING that will  
  actually relieve Traffic Congestion.
   
  Instead of spending $3 billion (prob $7 bil.) on a
   
  
  cost-ineffective 
  Transbay Terminal, 
   
  ( A statewide 
high-speed rail  
  bond set for the November 2004 election, would contribute $127 million. ) 
  lets spend it on something that will 
  directly
  reduce CONGESTION
  and air-pollution
  - the 
   19th 
  Ave Tunnel bypass
   
       | 
      
  
      
        | 
     
    
      | 
      Caltrans,  said 
      the estimated COST 
      of retrofitting or replacing 
      7 state 
      toll bridges, 
      including five in the Bay Area, climbed from:-
      
      
        $2.6 
        billion in 1997 
        to $4.7
        billion in 2001 (although 
        SF. Chron says 5.1 )
        to $7.4
        billion Aug
        2004 (not 
        including a $900 million contingency for future overruns) 
      
       The  bulk of those increases
       from $4.7 to $7.4 bil.--
      (all but 
      $286 million and $700 
      mil. on the   western 
      span) -- were on the new
      Eastern
      Span
      of the
      Bay Bridge 
      and 
      53% of that on 
      the selection of the 
      single-tower 
      suspension bridge, 
      unusual 
      features and 
      orthrotropic steel boxes, 
      totalling $4.4
      bil for the
      East 
      Side alone. 
      The remainder of the
      East 
      Side overruns
      (47%) 
      are attributable to increases in the costs of steel, 
      cement, bonding and insurance, and consolidation in the bridge 
      construction industry. 
      
      The cost for the  East 
      Span 
      was estimated at 
      $1.3 billion 
      before 2001 to 
      $2.6 
      in 2001 to 
      $4.4 bil. 
      2004, ($1.4 bil. for the 
      west side 
      and $1.6 bil. for the 
      6 other bridges). 
      
      Caltrans acknowledged that the cost had risen because of 
      bad estimates 
      and 
      design-caused delays.  | 
      
    
          
           The  2004,
          
    $7.4
          
    billion
          
          
          COST
          estimate 
          to retrofit  
          seven state-owned
          toll 
          Bridges
           
    including fixing
          the
          
          east 
          & west side
          
    of the San Francisco-Oakland Bay Bridge 
          is:-
          
            
      
        
          
          2004 
          mils. $ | 
          
          Bridge 
          (data fixed from SF Chron.) | 
          2001 
          mils. $ | 
         
            
        
          
          
    $4,400 
          
          not  5,130 
           | 
            
          
            
    East Side
            of the San Francisco-Oakland 
            Bay Bridge | 
            
          was $1,300 mil. before, then $2,600 mil 
           | 
         
            
        
          
    $1,400 
          
          not $737 
           | 
          West Side 
          
            of the San Francisco-Oakland Bay Bridge 
          retrofit, as a lifeline bridge | 
          
          was $700 mil then $737 mil. | 
         
            
        
          | 
    
            $180 | 
          
    
            Benicia-Martinez Bridge retrofit | 
          
    
            $190 | 
         
        
          | 
    
            $115 | 
          
    
          north span of the Carquinez retrofit 
           | 
          
    
            $125 | 
         
        
          | 
    
            $914 | 
          
    
            Richmond-San Rafael Bridge retrofit 
           | 
          
    
            $665 | 
         
        
          | 
    
            $165 | 
          
    
            San Mateo-Hayward Bridge retrofit 
           | 
          
    
            $190 | 
         
        
          | $62 | 
          
    
            San Pedro-Terminal Island Bridge retrofit | 
          
    
            $62 | 
         
        
          | $105 | 
          
    
            San Diego-Coronado Bridge retrofit | 
          
    
            $105 | 
         
        
          | 7,400 | 
          TOTAL | 
            4,674 | 
         
       
            
    
    | 
     
    
      | Gov. Arnold 
      Schwarzenegger: "It is Bay Area taxpayers sole responsibility 
      for meeting an estimated $2.3 billion in cost overruns to complete the Bay 
      Bridge project":
      
        Appoint an independent auditor to find out why it has taken 15 years 
        to complete the seismic retrofit, which includes constructing a new 
        eastern span. (2 years solely attributable 
        to Willie Brown)
        
        Nov. 2 ballot could ask Bay Area voters to 
        redirect 
        the 
        existing $1 
        Toll Increase 
        to cover 
        the bridge overruns (
        OR the 
        Metripolitan Transportation Commission (MTC) could divert already 
        allotted state funds for other projects to the bridge )
        Transfer responsibility for the retrofit project to the Metropolitan 
        Transportation Commission, MTC. 
      
      
       Caltrans  expected 
      bids from two joint ventures 
      and possibly a third. “I’m 
      surprised we only got one bid,” 
      adds the Metropolitan Transportation 
      Commission, “I do not know why the 
      contractors were on the sidelines on this project.” 
      Sources close to the bidding say a joint venture of Peter Kiewit Sons’ 
      Inc., Omaha, and Skanska Inc., Whitestone, N.Y., was another contender as 
      late as one month before the bid opening, but it did not ultimately bid. 
      “We were interested,” says Bruce Grewcock, Peter Kiewit chief operating 
      officer. 
      Kiewit itself was the sole bidder for an earlier bridge foundation 
      contract last year, which came in 63% over estimate (ENR 11/3/03 p. 10).
       The firm had won the 
      job in a rebid, with too low a figure. 
      
      Bidding executives point to the gyrating steel market for a structure 
      whose unique design and construction specs could require as much as 100 
      million lb of permanent steel and another 40 million lb of temporary steel 
      falsework, says Cagelis. “Individual pieces get very large,” he notes. 
      “You have to do it perfect the first time.” 
      Other reasons: Seismic requirements and location across a fault line, 
      tight tolerances, tough quality demands.  
      
      Because the self-anchored 
      suspension
      span is
      specified by state 
      legislation authorizing the bridge, legislative 
      approval would be required if Caltrans switched bridge types.
      “The best way to complete the bridge 
      is to stick with the bridge type and get to a point where you’re ready to 
      go,” McElhinney says. “Any additional time added to the schedule is cost 
      added to the structure.” Some speculate that
      significant redesign could add 
      up to four years to completion.  | 
      
       
      
        
      
      
      Twin concrete Viaducts  | 
     
    
      
        | 
     
   
  
  
    
    
      
        
          | 
           This could be an ideal 
          opportunity to  
          cut 80% from the spending of the $1 Toll 
          Increase, 
           
          cut 
          
          projects that will make relatively no difference 
          to
           
          Traffic Congestion.
           
          
          
            
            With little change to Traffic Congestion
            80% of the $'s, from the existing, new $1 bridge toll 
            increase, could be  
            re-directed towards the bridge 
            with little effect on congestion. (Of course we 
            still don't want the State to renege from paying their half too, 
  Arnold):-
            
              
              $787 
              on 
              RAIL including:
                $150 downtown Caltrain extension in San 
                Francisco 
                $143 BART Transbay Tube seismic strengthening
                
                $135 Commuter rail service over Dumbarton 
                rail bridge 
                $96 BART extension from Pittsburg/Baypoint 
                station east to Byron 
                $95 BART extension to Warm Springs 
                
                
                $35 "SMART" Rail Marin
              
              
              
              $107 FERRY
              $168 Other Transit 
               
              
              
              Contact your representatives click on "Find my District"
              
            
          
           | 
          
           the 20% Spending from the
          $1 Bridge Toll that 
          DOES
           
          Reduce Congestion Cost Effectively:-
          
          
            
            $65 I-580 rapid bus corridor improvements in 
            Dublin, Pleasanton, Livermore 
            Interchange improvement at U.S. 101 and Larkspur 
            ferry
            $35 Greenbrae Interchange
            $100 I-680/I-80/Highway 12 interchange 
            improvements in Solano County incl some of the following:
            $50 Benicia-Martinez Bridge: New Span
            $50 Interstate-80: Eastbound High-Occupancy 
            Vehicle (HOV) Lane Extension from Route 4 to Carquinez Bridge
            $50 Caldecott Tunnel Improvements. Provide funds 
            to plan and construct a fourth bore 
            $20 Solano County Express Bus. Curtola Park and 
            Ride, Benicia Intermodal Facility, Fairfield Transportation Center 
            and Vacaville Intermodal Station
            $65 AC connection to BART. Enhanced Bus-Phase 1 
            (International Blvd./Telegraph corridors)
            $22 Express Bus Service for San Mateo, Dumbarton, 
            and Bay Bridge
            Regional Express Bus - Richmond-San Rafael 
            Bridge, Carquinez, Benicia-Martinez and Antioch Bridge corridors.
            
          
           | 
         
        
          | 
    
          The Business, Transportation and 
          Housing Agency, 
          http://www.bth.ca.gov oversees CALTRANS. | 
          State law 
          prohibits Caltrans from accepting bids when it doesn't have the money 
          on hand to cover the full cost. Even if the voters approve paying for 
          it out of the new, existing $1 bridge toll in November election,
          Caltrans would not have 
          the money when the bid for the
          sleek new design 
          expires in September, 
          (expiration 
          of the lone bid for the 
          single-tower suspension section
          of the new bridge).  | 
         
         
     
    
  
  
  A  joint venture of American Bridge, 
  http://www.americanbridge.net/locations/cory.php 
  Nippon Steel Bridge
  and Fluor Corp. submitted a bid for 
  the Western 
  Side Retrofit in May 2004 of $1.8 
  billion using 
  domestic steel -- ($1.4 
  billion 
  if foreign steel is allowed).
  The bid far exceeded 
  Caltrans' estimate of $740 million. 
  because of the unique design, tough schedule, strict specifications and likely 
  flaws in developing and communicating the engineer’s estimate. Caltrans also 
  extended the construction schedule by 15 months.
  As Caltrans evaluates a $1.4 billion bid for the Western Retrofit, the 
  bidder is arguing against looking at any other bids. Another bid would delay 
  the project and boost costs, perhaps by hundreds of millions of dollars, the 
  lone bidder says. 
   
  A new bidding process will delay the project a year beyond the estimated 2010 
  ribbon cutting. U.S. trade regulations could add hundreds of millions of 
  dollars to the project cost. Federal rules require the use of domestic steel, 
  unless the price tag is 25 percent less with foreign steel - so the lower bid 
  (1.4) will prevail in this case. However, if the bidding reopens, current 
  foreign steel prices would allow domestic suppliers to beat the foreign steel 
  bid.  (Caltrans 
  has reopened bids in the past and received lower
  domestic 
  cost estimates, 
  still higher than foreign but now within the 25%). 
  
  
  SF Chron Article 
  
  http://www.sfgate.com/cgi-bin/article.cgi?file=/c/a/2004/08/17/MNGPB89CQ01.DTL
    
 |