$386
million in federal funds are set to go to 180 transportation projects in 95
jurisdictions across all nine Bay Area Counties through the One Bay Area Grant 2(OBAG
2) County Program.
source OBAG 2, which
also has a Regional Program, is the "policy framework" for MTC’s
distribution of $862 million in federal Surface Transportation Program
and Congestion Mitigation and Air Quality,
CMAQ,,
Improvement Program funds from
Fiscal Years 2017-18 to 2021-2022.
The majority of OBAG 2 funds will be directed to projects that will make
little difference to TRAFFIC CONGESTION:
-
15% bicycle and
pedestrian projects,
-
8% Safe Routes to School
-
34% Transportation for Livable Communities
projects, which are generally oriented to bicycle access and
walkability but also include streetscape improvements, road diets, or
transit elements.
The full list of OBAG2 County Program (One
Bay Area Grant (OBAG),
) project recommendations can be viewed either as a list (opposite)
or as a set of maps,
broken down by county.
Along with approval of the County Program project recommendations,
commissioners also approved revisions to the OBAG 2 Project Selection and
Programming Policy to clarify program details for the 80k by 2020 Challenge Grant initiative, a pilot
program to incentivize the production of affordable housing. These
revisions include:
- Increasing the
number of jurisdictions eligible to receive the challenge grant from 10 to
15;
- Clarifying that the preservation,
in addition to permitting, of affordable housing units will be
credited in the program;
Housing,
- Adding a provision that at least
one jurisdiction from each county will be awarded a challenge grant.
MTC’s continues to focus on reducing greenhouse gas emissions,
something that will happen if they do NOTHING.
They also "incentivizing the production and preservation of affordable
housing", and "giving local jurisdictions the flexibility to meet their
own transportation needs", among others.
The OBAG program is one of the primary mechanisms by which MTC is able to
implement the vision laid out in Plan
Bay Area 2040, the region’s long-range transportation and land use plan.
Documents
Project
Funding,
STP,
|
County |
Project Sponsor |
Project Name |
Project Type |
OBAG 2 Grant |
Alameda |
ACTC |
Alameda County SRTS Non‐Infrastructure Program |
SRTS |
$7,299,000 |
Alameda |
ACTC |
CMA Planning Activities |
Planning |
$8,289,000 |
Alameda |
Alameda |
Central Ave Complete Street |
TLC |
$3,487,000 |
Alameda |
Alameda |
City Wide Street Resurfacing Program |
LSR |
$827,000 |
Alameda |
Alameda |
Clement Ave Complete Street |
TLC |
$5,018,000 |
Alameda |
Alameda County |
Meekland Ave Corridor Improvement, Phase II |
TLC |
$9,300,000 |
Alameda |
Alameda County |
Various Streets and Roads Preservation |
FAS ‐ LSR |
$3,950,000 |
Alameda |
Albany |
San Pablo Ave and Buchanan St Pedestrian Improvements |
Bike/Ped |
$340,000 |
Alameda |
Berkeley |
North Shattuck Ave Rehabilitation |
LSR |
$1,214,000 |
Alameda |
Berkeley |
Southside Complete Streets & Transit Improvements |
TLC |
$7,121,000 |
Alameda |
Dublin |
Dublin Blvd Rehabilitation |
LSR |
$661,000 |
Alameda |
Emeryville |
Slurry Seal of Frontage Rd, 65th St, and Powell St |
LSR |
$225,000 |
Alameda |
Fremont |
Complete Streets Upgrade of Relinquished SR 84 in Centerville PDA |
TLC |
$7,695,000 |
Alameda |
Fremont |
Pavement Rehabilitation |
LSR |
$2,760,000 |
Alameda |
Hayward |
Main St Complete Street |
TLC |
$1,675,000 |
Alameda |
Hayward |
Winton Ave Complete Street |
LSR |
$1,750,000 |
Alameda |
Livermore |
Annual Pavement Maintenance |
LSR |
$1,382,000 |
Alameda |
MTC |
I‐580 Corridor Study |
Planning |
$200,000 |
Alameda |
Newark |
Thornton Ave Pavement Rehabilitation |
LSR |
$592,000 |
Alameda |
Oakland |
Citywide Paving Program |
LSR |
$4,895,000 |
Alameda |
Oakland |
Lakeside Family Streets |
Bike/Ped |
$4,792,000 |
Alameda |
Piedmont |
Oakland Ave Improvements |
LSR |
$168,000 |
Alameda |
Pleasanton |
Hacienda Business Park Pavement Rehabilitation |
LSR |
$1,095,000 |
Alameda |
San Leandro |
Washington Ave Rehabilitation |
LSR |
$1,048,000 |
Alameda |
Union City |
Dyer Rd Pavement Rehabilitation |
LSR |
$872,000 |
|
|
Alameda County Total |
|
$76,655,000 |
Contra Costa |
Antioch |
L St Pathway to Transit |
SRTS |
$1,223,000 |
Contra Costa |
Antioch |
Pavement Rehabilitation |
LSR |
$2,474,000 |
Contra Costa |
Brentwood |
Various Streets and Roads Preservation |
LSR |
$1,653,000 |
Contra Costa |
CCTA |
CMA Planning Activities |
Planning |
$4,342,000 |
Contra Costa |
Clayton |
Neighborhood Streets Rehabilitation |
LSR |
$308,000 |
Contra Costa |
Concord |
Monument Blvd Class I Path |
Bike/Ped |
$4,368,000 |
Contra Costa |
Concord |
Willow Pass Repaving & SRTS |
LSR & SRTS |
$5,260,000 |
Contra Costa |
Contra Costa |
Kirker Pass Rd Overlay |
FAS ‐ LSR |
$1,343,000 |
Contra Costa |
Contra Costa |
Local Streets and Roads Preservation |
LSR |
$4,327,000 |
Contra Costa |
Contra Costa |
West County Walk and Bike Leaders (Non‐Infrastructure) |
SRTS |
$561,000 |
Contra Costa |
Danville |
Camino Ramon Improvements |
LSR |
$1,357,000 |
Contra Costa |
El Cerrito |
Carlson Blvd and Central Ave Pavement Rehabilitation |
LSR |
$544,000 |
Contra Costa |
El Cerrito |
El Cerrito del Norte TOD Complete Streets Improvements |
TLC |
$4,840,000 |
Contra Costa |
Hercules |
Sycamore/Willow Pavement Rehabilitation |
LSR |
$492,000 |
Contra Costa |
Lafayette |
Pleasant Hill Rd Pavement Rehabilitation |
LSR |
$579,000 |
Contra Costa |
Martinez |
Dowtown Streets Rehabilitation |
LSR |
$846,000 |
Contra Costa |
Moraga |
Moraga Way and Canyon Rd/Camino Pablo Improvements |
LSR |
$1,203,000 |
Contra Costa |
Oakley |
Vintage Parkway Rehabilitation |
LSR |
$969,000 |
Contra Costa |
Orinda |
Orinda Way Pavement Rehabilitation |
LSR |
$620,000 |
Contra Costa |
Pinole |
San Pablo Ave Rehabilitation |
LSR |
$586,000 |
Contra Costa |
Pittsburg |
BART Pedestrian and Bicycle Connectivity |
Bike/Ped |
$3,870,000 |
Contra Costa |
Pittsburg |
Pavement Improvements |
LSR |
$1,385,000 |
Contra Costa |
Pleasant Hill |
Pleasant Hill Rd Improvements |
LSR |
$920,000 |
Contra Costa |
Richmond |
ADA Improvements on 7th, Central, Cutting, Giant Hwy |
LSR |
$2,205,000 |
Contra Costa |
Richmond |
Lincoln Elementary SRTS Pedestrian Enhancements |
SRTS |
$320,000 |
Contra Costa |
San Pablo |
Market St Pavement Rehabilitation |
LSR |
$618,000 |
Contra Costa |
San Ramon |
Alcosta Blvd Pavement Rehabilitation |
LSR |
$1,175,000 |
Contra Costa |
San Ramon |
Iron Horse Bike and Pedestrian Overcrossings |
Bike/Ped |
$4,840,000 |
Contra Costa |
San Ramon |
San Ramon Valley Street Smarts (Non‐Infrastructure) |
SRTS |
$300,000 |
Contra Costa |
Walnut Creek |
Ygnacio Valley & Oak Grove Rd Rehabilitation |
LSR |
$2,608,000 |
|
|
Contra Costa
County Total |
|
$56,136,000 |
Marin |
Corte Madera |
Paradise Drive Muliti‐Use Path, San Clement Dr to Seawolf
Passage |
SRTS |
$595,000 |
Marin |
GGBHTD |
San Rafael Bettini Transit Center |
TLC |
$1,250,000 |
Marin |
Novato |
Nave Dr, Bel Marin Keys Blvd Preservation (for Novato Downtown
SMART) |
LSR (TLC) |
$1,450,000 |
Marin |
San Anselmo |
San Anselmo Bike Spine |
SRTS |
$269,000 |
Marin |
San Anselmo |
Sir Francis Drake Blvd Pavement Rehab and Crossing
Improvements |
LSR |
$1,134,000 |
Marin |
San Rafael |
Francisco Blvd East Sidewalk Improvements |
Bike/Ped |
$2,100,000 |
Marin |
Sausalito |
US 101/Bridgeway/Gate 6 Bicycle Improvements |
Bike/Ped |
$250,000 |
Marin |
TAM |
CMA Planning Activities |
Planning |
$3,822,000 |
|
|
Marin County
Total |
|
$10,870,000 |
Napa |
American Canyon |
Green Island Rd Improvements |
LSR |
$1,000,000 |
Napa |
City of Napa |
Silverado Trail Five‐way Intersection Improvement |
TLC |
$2,000,000 |
Napa |
NVTA |
CMA Planning Activities |
Planning |
$3,822,000 |
Napa |
NVTA |
Napa County SRTS Non‐Infrastructure Program |
SRTS |
$122,000 |
Napa |
St. Helena |
Main St Pedestrian Improvements |
Bike/Ped |
$1,206,000 |
|
|
Napa County
Total |
|
$8,150,000 |
San Francisco |
BART |
Embarcadero Station New Northside Platform Elevator and
Faregates |
TLC |
$2,000,000 |
San Francisco |
PCJPB |
Peninsula Corridor Electrification |
TLC |
$11,188,000 |
San Francisco |
SFCTA |
CMA Planning Activities |
Planning |
$5,897,000 |
San Francisco |
SFMTA |
Geary Bus Rapid Transit Phase 1 |
TLC |
$6,939,000 |
San Francisco |
SFPW |
Better Market St Improvements |
Other/Multi‐ |
$15,980,000 |
San Francisco |
SFPW |
John Yehall Chin Elementary SRTS |
SRTS |
$3,366,000 |
San Francisco |
TBD |
Unprogrammed SRTS program/project |
SRTS |
$2,813,000 |
|
|
San
Francisco County Total |
|
$48,183,000 |
San Mateo |
Atherton |
Middlefield Rd Class II Bike Lanes |
LSR |
$251,000 |
San Mateo |
Belmont |
Ralston Ave Corridor Bike/Ped Improvements |
Bike/Ped |
$1,000,000 |
San Mateo |
Belmont |
Various Streets Pavement Rehabilitation |
LSR |
$467,000 |
San Mateo |
Brisbane |
Crocker Trail Commuter Connectivity Upgrades |
Bike/Ped |
$885,000 |
San Mateo |
Brisbane |
Tunnel Ave Rehabilitation |
LSR |
$137,000 |
San Mateo |
Burlingame |
Broadway PDA Lighting Improvements |
TLC |
$720,000 |
San Mateo |
Burlingame |
Hoover School Area Sidewalk Improvements |
Bike/Ped |
$700,000 |
San Mateo |
Burlingame |
Various Street Resurfacing |
LSR |
$571,000 |
San Mateo |
C/CAG |
CMA Planning Activities |
Planning |
$5,334,000 |
San Mateo |
C/CAG |
San Mateo County SRTS Non‐Infrastructure Program |
SRTS |
$2,617,000 |
San Mateo |
Colma |
Mission Rd Bicycle/Pedstrian Improvements |
TLC |
$625,000 |
San Mateo |
Daly City |
Various Streets Pavement Resurfacing and Slurry Seal |
LSR |
$1,310,000 |
San Mateo |
East Palo Alto |
Various Streets Resurfacing |
LSR |
$416,000 |
San Mateo |
Foster City |
Various Streets Pavement Rehabilitation |
LSR |
$441,000 |
San Mateo |
Half Moon Bay |
Poplar St Complete Streets |
TLC |
$1,202,000 |
San Mateo |
Hillsborough |
Various Streets Resurfacing |
LSR |
$408,000 |
San Mateo |
Menlo Park |
Santa Cruz and Middle Avenues Rehabilitation |
LSR |
$647,000 |
San Mateo |
Millbrae |
Various Streets Pavement Rehabilitation |
LSR |
$387,000 |
San Mateo |
Pacifica |
Citywide Curb Ramp Replacements |
Bike/Ped |
$400,000 |
San Mateo |
Pacifica |
Palmetto Sidewalk Improvements |
Bike/Ped |
$330,000 |
San Mateo |
Pacifica |
Various Streets Pavement Rehabilitation |
LSR |
$671,000 |
San Mateo |
Portola Valley |
Various Streets Resurfacing |
LSR |
$201,000 |
San Mateo |
Redwood City |
Twin Dolphin Parkway Overlay |
LSR |
$1,266,000 |
San Mateo |
Redwood City |
US 101/Woodside Rd Class I Bikeway |
Bike/Ped |
$948,000 |
San Mateo |
San Bruno |
Huntington Transit Corridor Bicycle/Pedestrian and
Related Imps |
Bike/Ped |
$914,000 |
San Mateo |
San Bruno |
Various Streets Pavement Rehabilitation |
LSR |
$673,000 |
San Mateo |
San Carlos |
Cedar and Brittan Ave Pavement Rehabilitation |
LSR |
$575,000 |
San Mateo |
San Carlos |
Ped Enhancements Arroyo/Cedar and Hemlock/Orange |
TLC |
$500,000 |
San Mateo |
San Carlos |
US 101/Holly Street Bike/Ped Overcrossing |
Bike/Ped |
$1,000,000 |
San Mateo |
San Mateo |
Laurie Meadows Ped/Bike Safety Improvements |
TLC |
$987,000 |
San Mateo |
San Mateo |
Various Streets Pavement Rehabilitation |
LSR |
$1,593,000 |
San Mateo |
San Mateo County |
Canada Rd and Edgewood Rd Resurfacing |
FAS ‐ LSR |
$892,000 |
San Mateo |
San Mateo County |
Countywide Pavement Maintenance |
LSR |
$1,072,000 |
San Mateo |
South San |
Grand Boulevard Initiative Complete Street Imps |
TLC |
$1,000,000 |
San Mateo |
South San |
Various Streets Pavement Rehabilitation |
LSR |
$1,027,000 |
San Mateo |
Woodside |
Various Streets Pavement Rehabilitation |
LSR |
$242,000 |
San Mateo |
Woodside |
Woodside Pathway Phase 3 |
Bike/Ped |
$136,000 |
|
|
San
Mateo County Total |
|
$32,545,000 |
Santa Clara |
Campbell |
Eden Ave Sidewalk Improvements |
SRTS |
$555,000 |
Santa Clara |
Campbell |
Winchester Blvd Overlay |
LSR |
$554,000 |
Santa Clara |
Cupertino |
Cupertino Pavement Management Program |
LSR |
$769,000 |
Santa Clara |
Gilroy |
Downtown Monterey St Rehabilitation |
LSR |
$1,028,000 |
Santa Clara |
Los Altos |
Fremont Ave Asphalt Concrete Overlay |
LSR |
$336,000 |
Santa Clara |
Los Gatos |
Los Gatos Creek Trail to Highway 9 Trailhead
Connection |
Bike/Ped |
$343,000 |
Santa Clara |
Milpitas |
Street Resurfacing |
LSR |
$1,609,000 |
Santa Clara |
Morgan Hill |
East Dunne Ave Pavement Rehabilitation |
LSR |
$857,000 |
Santa Clara |
Mountain View |
West Middlefield Road Improvements |
LSR |
$1,136,000 |
Santa Clara |
Palo Alto |
Adobe Creek/Highway 101 Bicycle Pedestrian Bridge |
Bike/Ped |
$4,350,000 |
Santa Clara |
Palo Alto |
El Camino Real Pedestrian Safety and Streetscape
Improvements |
Bike/Ped |
$4,655,000 |
Santa Clara |
Palo Alto |
North Ventura Coordinated Area Plan |
Planning |
$638,000 |
Santa Clara |
Palo Alto |
Street Resurfacing |
LSR |
$1,009,000 |
Santa Clara |
Palo Alto |
Waverley, E. Meadow & Fabian Enhanced Bikeways |
SRTS |
$919,000 |
Santa Clara |
San Jose |
Downtown San Jose Mobility Streetscape and Public
Life Plan |
Planning |
$813,000 |
Santa Clara |
San Jose |
East Side Alum Rock (east of 680) Urban Village
Plan |
Planning |
$400,000 |
Santa Clara |
San Jose |
McKee Rd Vision Zero Priority Safety Corridor
Improvements |
TLC |
$8,623,000 |
Santa Clara |
San Jose |
Mount Pleasant Pedestrian & Bicycle Traffic Safety
Improvements |
SRTS |
$1,000,000 |
Santa Clara |
San Jose |
Pavement Maintenance Program |
LSR |
$14,597,000 |
Santa Clara |
San Jose |
Tully Rd Vision Zero Priority Safety Corridor
Improvements |
TLC |
$8,599,000 |
Santa Clara |
San Jose |
W San Carlos Urban Village Streetscape
Improvements |
TLC |
$5,632,000 |
Santa Clara |
Santa Clara |
Hetch‐Hetchy Trail Phase 1 |
Bike/Ped |
$790,000 |
Santa Clara |
Santa Clara |
San Tomas Aquino Creek Trail Underpass |
Bike/Ped |
$2,449,000 |
Santa Clara |
Santa Clara |
Saratoga Creek Trail Phase 1 |
Bike/Ped |
$2,735,000 |
Santa Clara |
Santa Clara |
School Access Improvements |
SRTS |
$1,146,000 |
Santa Clara |
Santa Clara |
Streets & Roads Preservation |
LSR |
$2,356,000 |
Santa Clara |
Santa Clara County |
Capitol Expressway Pavement Rehabilitation |
LSR |
$5,000,000 |
Santa Clara |
Santa Clara County |
McKean Rd Pavement Rehabilitation |
LSR |
$1,151,000 |
Santa Clara |
Santa Clara County |
Uvas Rd Pavement Rehabilitation |
FAS ‐ LSR |
$1,701,000 |
Santa Clara |
Saratoga |
Saratoga Village Crosswalks and Sidewalk
Rehabilitation |
LSR |
$338,000 |
Santa Clara |
Sunnyvale |
Bernardo Avenue Bicycle Underpass ‐ EIR |
Bike/Ped |
$500,000 |
Santa Clara |
Sunnyvale |
East Sunnyvale Area Sense of Place Improvements |
Bike/Ped |
$3,047,000 |
Santa Clara |
Sunnyvale |
Fair Oaks Avenue Bikeway ‐ Phase 2 |
Bike/Ped |
$782,000 |
Santa Clara |
Sunnyvale |
Homestead Rd at Homestead High School Pedestrian &
Bicycle Improvements |
SRTS |
$1,000,000 |
Santa Clara |
Sunnyvale |
Java Dr Road Diet and Bike Lanes |
Bike/Ped |
$500,000 |
Santa Clara |
Sunnyvale |
Lawerence Station Area Sidewalks & Bike Facilities |
Bike/Ped |
$500,000 |
Santa Clara |
Sunnyvale |
Pedestrian and Bicycle Infrastructure Improvements |
SRTS |
$919,000 |
Santa Clara |
Sunnyvale |
Peery Park Sense of Place Improvements |
Bike/Ped |
$2,686,000 |
Santa Clara |
Sunnyvale |
Traffic Signal Upgrades |
LSR |
$2,566,000 |
Santa Clara |
VTA |
CMA Planning Activities |
Planning |
$10,900,000 |
Santa Clara |
VTA/Milpitas |
Montague Expressway Pedestrian Bridge at Milpitas
BART |
Bike/Ped |
$3,560,000 |
Santa Clara |
TBD |
Unprogrammed SRTS Program/Project |
SRTS |
$1,000,000 |
Santa Clara |
TBD |
Unprogrammed balance |
‐ |
$25,000 |
|
|
|
San Clara |
$104,073,000 |
Solano |
Benicia |
Park Rd Improvements |
Bike/Ped |
$2,731,000 |
Solano |
Fairfield |
Grange Middle School SRTS Improvements |
SRTS |
$260,000 |
Solano |
Solano County |
County Roads Paving |
FAS ‐ LSR |
$506,000 |
Solano |
Solano County |
Farm to Market Phase 2 Improvements |
FAS ‐ LSR |
$1,000,000 |
Solano |
STA |
CMA Planning Activities |
Planning |
$6,861,000 |
Solano |
STA |
Solano County SRTS Non‐Infrastructure
Program |
SRTS |
$1,209,000 |
Solano |
STA |
Solano Mobility Call Center |
TLC |
$1,537,000 |
Solano |
STA/Vacaville |
Jepson Parkway Phase 3 Bike Path |
Bike/Ped |
$1,407,000 |
Solano |
Suisun City |
Railroad Ave Repaving |
LSR |
$491,000 |
Solano |
Vacaville |
VacaValley/I‐505 Ramps Roundabouts |
Bike/Ped |
$1,907,000 |
Solano |
Vacaville |
Various Streets Overlay |
LSR |
$1,193,000 |
Solano |
Vallejo |
Various Streets Overlay |
LSR |
$2,075,000 |
|
|
Solano County Total |
|
$21,177,000 |
Sonoma |
Cotati |
E Cotati Ave Rehabilitation |
LSR |
$675,000 |
Sonoma |
Healdsburg |
Healdsburg Ave Road Diet |
LSR |
$600,000 |
Sonoma |
Petaluma |
Petaluma Blvd South Road Diet |
LSR |
$2,916,000 |
Sonoma |
Rohnert Park |
Various Streets Rehabilitation |
LSR |
$1,035,000 |
Sonoma |
Santa Rosa |
US 101 Bicycle and Pedestrian Bridge
Overcrossing |
Bike/Ped |
$1,418,000 |
Sonoma |
Santa Rosa |
Various Streets Rehabilitation |
LSR |
$1,655,000 |
Sonoma |
SCTA |
CMA Planning Activities |
Planning |
$5,000,000 |
Sonoma |
SCTA |
Countywide SRTS Non‐Infrastructure Program |
SRTS |
$1,655,000 |
Sonoma |
Sebastopol |
Bodega Ave Bike Lanes and Pavement
Rehabilitation |
LSR |
$1,195,000 |
Sonoma |
SMART |
Petaluma SMART Pathway |
Bike/Ped |
$400,000 |
Sonoma |
Sonoma |
Fryer Creek Bicycle and Pedestrian Bridge |
Bike/Ped |
$501,000 |
Sonoma |
Sonoma County |
Crocker Bridge Bike and Pedestrian Passage |
Bike/Ped |
$1,809,000 |
Sonoma |
Sonoma County |
River Rd Pavement Rehabilitation |
FAS ‐ LSR |
$3,264,000 |
Sonoma |
Sonoma County |
Various County Roads Rehabilitation |
LSR |
$2,600,000 |
Sonoma |
Windsor |
Windsor River Rd at Windsor Rd
Intersection Improvements |
LSR |
$3,000,000 |
|
|
Sonoma County Total |
|
$27,723,000 |
|
|
OBAG 2 County Program Total |
|
$385,512,000 |
|